Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0224-00263
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
6347 S FONTANA AV
Address NEW:
6347 S FONTANA AV
Apply Date:
02/08/2024
Applicant:
Description:
“Each unit is existing, there are no new units or buildings”. Per the electrical plans "A" electrical service is a replacement, MH pedestals 1 -thru- 5. The verification of the address is included, Service is to ensure the meter clearances are accepted and approved by the electrical utility (TEP). Each service "A, B, C, D and E, which requires its individual permit and is being represented as such. ‘Electrical Pedestals are being installed in place of the existing poles and connected to each of the 28 ‘Existing Units’ sub-meters.
Permit Reviews
Permit Number - TC-COM-0224-00263
Permit Status: Complete
Permit Description: “Each unit is existing, there are no new units or buildings”. Per the electrical plans "A" electrical service is a replacement, MH pedestals 1 -thru- 5. The verification of the address is included, Service is to ensure the meter clearances are accepted and approved by the electrical utility (TEP). Each service "A, B, C, D and E, which requires its individual permit and is being represented as such. ‘Electrical Pedestals are being installed in place of the existing poles and connected to each of the 28 ‘Existing Units’ sub-meters.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/08/2024 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 02/15/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0224-00263
Permit Status: Complete
Permit Description: “Each unit is existing, there are no new units or buildings”. Per the electrical plans "A" electrical service is a replacement, MH pedestals 1 -thru- 5. The verification of the address is included, Service is to ensure the meter clearances are accepted and approved by the electrical utility (TEP). Each service "A, B, C, D and E, which requires its individual permit and is being represented as such. ‘Electrical Pedestals are being installed in place of the existing poles and connected to each of the 28 ‘Existing Units’ sub-meters.
| Date | Description | Comments |
|---|---|---|
| 02/08/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00263
Permite Description: “Each unit is existing, there are no new units or buildings”. Per the electrical plans "A" electrical service is a replacement, MH pedestals 1 -thru- 5. The verification of the address is included, Service is to ensure the meter clearances are accepted and approved by the electrical utility (TEP). Each service "A, B, C, D and E, which requires its individual permit and is being represented as such. ‘Electrical Pedestals are being installed in place of the existing poles and connected to each of the 28 ‘Existing Units’ sub-meters.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | Called multiple times got in touch with point of contact and didn't receive a call back for the inspection. 5/6/2024 |
| 10/21/2024 | COT - LCEL - Electrical Final | N/A | Re-inspection required | 10/21/24: called number provided no answer. Arrived onsite no one present for inspection. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00263
Permit Description: “Each unit is existing, there are no new units or buildings”. Per the electrical plans "A" electrical service is a replacement, MH pedestals 1 -thru- 5. The verification of the address is included, Service is to ensure the meter clearances are accepted and approved by the electrical utility (TEP). Each service "A, B, C, D and E, which requires its individual permit and is being represented as such. ‘Electrical Pedestals are being installed in place of the existing poles and connected to each of the 28 ‘Existing Units’ sub-meters.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2024 | COT - LCEL - Grounding/Bonding | Passed | 2/23/24: electrical underground per plan, grounding at pedestals passed. | |
| 02/23/2024 | COT - LCEL - Electrical Underground | Passed | 2/23/24: electrical underground per plan, grounding at pedestals passed. | |
| 05/10/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. UNIT A. 5/10/2024 | |
| 10/21/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
| 10/21/2024 | COT - LCEL - Electrical Final | Passed |