Status:
Complete
Type:
Commercial Building
Apply Date:
02/14/2023
Applicant:
Miriam Desroches
Description:
Ground up, new construction for a smoothie shop. 1,593 S.F. BUILDING + 105 SF EXTERIOR WALK-IN Development Package #: TD-DEV-0223-00135

Permit Reviews

Permit Number - TC-COM-0223-00646
Permit Status: Complete
Permit Description: Ground up, new construction for a smoothie shop. 1,593 S.F. BUILDING + 105 SF EXTERIOR WALK-IN Development Package #: TD-DEV-0223-00135
Start Date Submittal Complete Date Status  
10/30/2023 COMMERCIAL REVIEW - FULL v.6 11/02/2023 APPROVED Review Details
06/29/2023 COMMERCIAL REVIEW - FULL v.2 07/14/2023 REQUIRES RESUBMIT Review Details
11/19/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/19/2024 APPROVED Review Details
12/01/2023 COMMERCIAL REVIEW - FULL v.1 12/27/2023 REQUIRES RESUBMIT Review Details
09/19/2023 COMMERCIAL REVIEW - FULL v.4 10/04/2023 REQUIRES RESUBMIT Review Details
02/15/2024 RESTAMP - COMMERCIAL v.1 02/26/2024 APPROVED Review Details
11/04/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/04/2024 REQUIRES RESUBMIT Review Details
10/23/2023 COMMERCIAL REVIEW - FULL v.5 10/23/2023 REQUIRES RESUBMIT Review Details
09/01/2023 COMMERCIAL REVIEW - FULL v.3 09/07/2023 REQUIRES RESUBMIT Review Details
12/03/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/04/2024 APPROVED Review Details
12/09/2024 COMMERCIAL REVIEW - FULL REVISION v.1 12/17/2024 APPROVED Review Details
12/17/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/20/2024 APPROVED Review Details
02/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/05/2024 APPROVED Review Details
03/01/2023 COMMERCIAL REVIEW - FULL v.1 03/23/2023 REQUIRES RESUBMIT Review Details
09/25/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/25/2024 APPROVED Review Details
11/02/2023 RESTAMP - COMMERCIAL v.1 11/06/2023 APPROVED Review Details
02/09/2024 COMMERCIAL REVIEW - FULL v.2 02/15/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-0223-00646
Permit Status: Complete
Permit Description: Ground up, new construction for a smoothie shop. 1,593 S.F. BUILDING + 105 SF EXTERIOR WALK-IN Development Package #: TD-DEV-0223-00135
Date Description Comments
11/02/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
10/15/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/15/2024 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
10/15/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/15/2024 Do not issue C of O until Final Plat TD-DIV-0123-0035 is approved by Mayor & Council and is recorded.
10/15/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
10/15/2024 Kitchen Hood Fire Suppression Designs must be submitted and approved prior to final.
11/26/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
10/15/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
10/15/2024 Please submit a separate sign permit for an signs associated with this projet.
10/15/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
12/02/2024 No TCO/C of O will be issued until Outdoor Lighting submittal has been approved and Outdoor Lighting Special Inspection has be submitted for review and passed.
11/02/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
11/02/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0223-00646
Permite Description: Ground up, new construction for a smoothie shop. 1,593 S.F. BUILDING + 105 SF EXTERIOR WALK-IN Development Package #: TD-DEV-0223-00135
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
02/07/2024 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass ok to install pop outs
02/07/2024 COT - HCBU - Framing N/A Not Ready
07/31/2024 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass
07/31/2024 COT - HCEL - Electrical Underground N/A Partial Pass
12/16/2024 COT - HCME - Mechanical Final N/A Partial Pass 12/16/24: ADA requirements at bathrooms not met, properly seal roof penetrations at chiller/freezer, fuse size at chiller/freezer not appropriate size, roof drain covers required. pending conditions. OK FOR LEVEL 2 TCO.
12/16/2024 COT - HCPL - Plumbing Final N/A Partial Pass 12/16/24: ADA requirements at bathrooms not met, properly seal roof penetrations at chiller/freezer, fuse size at chiller/freezer not appropriate size, roof drain covers required. pending conditions. OK FOR LEVEL 2 TCO.
12/16/2024 COT - HCBU - Building Final N/A Partial Pass 12/16/24: ADA requirements at bathrooms not met, properly seal roof penetrations at chiller/freezer, fuse size at chiller/freezer not appropriate size, roof drain covers required. pending conditions. OK FOR LEVEL 2 TCO.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0223-00646
Permit Description: Ground up, new construction for a smoothie shop. 1,593 S.F. BUILDING + 105 SF EXTERIOR WALK-IN Development Package #: TD-DEV-0223-00135
Total Completed Inspections - 37
Date Description Inspector Results Comments
01/17/2024 COT - HCBU - Preslab Passed
02/07/2024 COT - HCBU - Roof Nailing Passed
03/06/2024 COT - HCBU - Interior Shear Bracing Passed
03/06/2024 COT - HCPL - Gas Pressure Test Passed
03/06/2024 COT - HCBU - Exterior Clips/Sheathing Passed
03/20/2024 COT - HCBU - Framing Passed
03/20/2024 COT - HCEL - Electrical Intermediate Passed
03/20/2024 COT - HCPL - Plumbing Intermediate Passed
03/20/2024 COT - HCPL - Plumbing Roof Drains Passed
03/27/2024 COT - HCPL - Plumbing Above Ceiling Passed
04/23/2024 COT - HCPL - Backwater Valve Passed
04/23/2024 COT - HCPL - Rough Soil Passed
04/23/2024 COT - HCPL - Sewer Passed
04/30/2024 COT - HCPL - Yard Water Line Passed 4/30/24: Main water line under pressure. Ok to backfill. Shading required
06/18/2024 COT - HCBU - Building Above Ceiling Passed
06/18/2024 COT - HCEL - Electrical Above Ceiling Passed
06/18/2024 COT - HCME - Mechanical Above Ceiling Passed
10/15/2024 BULD - Electrical Clearance Passed 10/11/24: TEP ECO CLEARANCE FOR 1620 E TUCSON MARKETPLACE BL
10/16/2024 COT - HCEL - Grounding/Bonding Passed
11/15/2024 COT - BULD - SWG Clearance Passed 11/15/24: SWG CLEARANCE FOR METER TAG.
12/12/2024 COT - FCON - Fire - Final Passed
12/13/2024 TRSP - ROW - Final/Close-Out Passed
12/16/2024 COT - HCBU - Excavation/Rebar/Zoning Passed
12/16/2024 COT - HCBU - Firewall/Fire Barrier/Firestop Passed
12/16/2024 COT - HCBU - Stem Wall/Retaining Wall Passed
12/16/2024 COT - HCEL - Electrical Underground Passed
12/16/2024 COT - HCME - Mechanical Intermediate Passed
12/16/2024 COT - HCME - Venting Passed
12/16/2024 COT - HCPL - Gas Final Passed
12/17/2024 ENGR Engineering Final Passed Signs, menu board, clearance bar and drive through exit sign by others.
12/16/2024 COT - HCEL - Electrical Final Passed
12/16/2024 COT - HCEL - Outdoor Lighting Passed
12/19/2024 PDSD Heavy Commercial Building Division Pre-Construction Meeting Passed
12/19/2024 COT - HCME - Mechanical Final Passed
12/19/2024 COT - HCPL - Plumbing Final Passed
12/19/2024 COT - HCBU - CofO Passed
01/10/2025 COT - HCBU - Building Final Passed