Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Inspections
Type:
Commercial Building
Address:
3300 S PARK AV
Address NEW:
3300 S PARK AV
Apply Date:
01/29/2026
Applicant:
Description:
New flatwork and shade structure in the courtyard between two buildings and repair beam

Permit Reviews

Permit Number - TC-COM-0126-00131
Permit Status: Inspections
Permit Description: New flatwork and shade structure in the courtyard between two buildings and repair beam
Start Date Submittal Complete Date Status  
04/21/2026 COMMERCIAL REVIEW - LIMITED v.3 05/12/2026 REQUIRES RESUBMIT Review Details
05/13/2026 RESTAMP - COMMERCIAL v.1 05/14/2026 APPROVED Review Details
02/02/2026 COMMERCIAL REVIEW - LIMITED v.1 02/18/2026 REQUIRES RESUBMIT Review Details
04/06/2026 COMMERCIAL REVIEW - LIMITED v.2 04/06/2026 REQUIRES RESUBMIT Review Details
05/15/2026 SPECIAL INSPECTION REVIEW v.1 05/19/2026 APPROVED Review Details
05/13/2026 COMMERCIAL REVIEW - LIMITED v.4 05/13/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0126-00131
Permit Status: Inspections
Permit Description: New flatwork and shade structure in the courtyard between two buildings and repair beam
Total Outstanding Activity Conditions - 3
Date Name
02/12/2026 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
02/12/2026 SPECIAL INSPECTION OF WELDING IS REQUIRED.
04/23/2026 Shade canopy designs must be submitted and approved prior to installation and Final Instection

Conditions

Permit Number - TC-COM-0126-00131
Permit Status: Inspections
Permit Description: New flatwork and shade structure in the courtyard between two buildings and repair beam
Date Description Comments
04/23/2026 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
02/02/2026 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
05/14/2026 Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit.
02/02/2026 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/23/2026 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-0126-00131
Permite Description: New flatwork and shade structure in the courtyard between two buildings and repair beam
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
08/28/2026 COT - LCBU - Preslab N/A Not Applicable 8-28-26: concrete benches removed from plans-No concrete pour on this permit.
08/27/2026 COT - LCBU - Excavation/Rebar/Zoning N/A Not Ready Inspection type was for flat work. Schedule correct inspection. 8/27/2026
09/18/2026 COT - LCBU - Building Final N/A Partial Pass 9/18/26: OKAY TO REQUEST LEVEL 4 TCO.
09/17/2026 COT - FCON - Fire - Final N/A Not Applicable
09/18/2026 ENGR Engineering Final N/A Partial Pass Okay to apply for level 4 TCO

Completed Inspections

Permit Status: Inspections
Permit Number: TC-COM-0126-00131
Permit Description: New flatwork and shade structure in the courtyard between two buildings and repair beam
Total Completed Inspections - 5
Date Description Inspector Results Comments
09/14/2026 COT - LCEL - Electrical Final Passed
09/14/2026 COT - LCEL - Electrical Intermediate Passed
09/17/2026 COT - LCEL - Outdoor Lighting Passed
09/17/2026 Passed
09/18/2026 COT - LCBU - Framing Passed