Permit: TC-COM-0125-00181
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
6924 E SPEEDWAY BL
Address NEW:
6924 E SPEEDWAY BL
Apply Date:
01/28/2025
Applicant:
Damon GIGLIO
Description:
Converting an existing enclosed storage building adjacent to a community pool to a semi-open raised patio/deck. 385 SF of original storage building plus new 289 SF for expanded deck area.
Permit Reviews
Permit Number - TC-COM-0125-00181
Permit Status: Inspections
Permit Description: Converting an existing enclosed storage building adjacent to a community pool to a semi-open raised patio/deck. 385 SF of original storage building plus new 289 SF for expanded deck area.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/04/2025 | COMMERCIAL REVIEW - LIMITED v.2 | 04/21/2025 | APPROVED |
| 02/01/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 02/14/2025 | REQUIRES RESUBMIT |
| 04/21/2025 | RESTAMP - COMMERCIAL v.1 | 04/23/2025 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0125-00181
Permite Description: Converting an existing enclosed storage building adjacent to a community pool to a semi-open raised patio/deck. 385 SF of original storage building plus new 289 SF for expanded deck area.
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2025 | COT - LCBU - Building Final | N/A | Not Ready | 8-11-25: work on storage conversion not started. No point of contact information located on notes and employee on site did not have contractor's contact information either. Reschedule when ready. |
| 08/11/2025 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | 8-11-25: work on storage conversion not started. No point of contact information located on notes and employee on site did not have contractor's contact information either. Reschedule when ready. |
| 08/11/2025 | COT - LCBU - Framing | N/A | Not Ready | 8-11-25: work on storage conversion not started. No point of contact information located on notes and employee on site did not have contractor's contact information either. Reschedule when ready. |
| 08/11/2025 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | 8-11-25: work on storage conversion not started. No point of contact information located on notes and employee on site did not have contractor's contact information either. Reschedule when ready. |
| 08/11/2025 | COT - LCBU - Preslab | N/A | Not Ready | 8-11-25: work on storage conversion not started. No point of contact information located on notes and employee on site did not have contractor's contact information either. Reschedule when ready. |
| 08/11/2025 | COT - LCBU - Roof Nailing | N/A | Not Ready | 8-11-25: work on storage conversion not started. No point of contact information located on notes and employee on site did not have contractor's contact information either. Reschedule when ready. |