Permit: TC-COM-0125-00096
Permit Details
Apply Date:
01/15/2025
Applicant:
Jaris Brenneman
Description:
Coffee Wow Phase 2: Updated equipment and millwork to existing coffee bar. Installation of new drain manifold serving the coffee bar. Added dedicated water line and circuit for coffee wow auto clean system. Add glycol chiller and nitrogen generator for nitro coffee.
Permit Reviews
Permit Number - TC-COM-0125-00096
Permit Status: Complete
Permit Description: Coffee Wow Phase 2: Updated equipment and millwork to existing coffee bar.
Installation of new drain manifold serving the coffee bar.
Added dedicated water line and circuit for coffee wow auto clean system.
Add glycol chiller and nitrogen generator for nitro coffee.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/27/2025 | COMMERCIAL REVIEW - LIMITED v.2 | 03/13/2025 | REQUIRES RESUBMIT |
| 01/21/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 02/04/2025 | REQUIRES RESUBMIT |
| 03/27/2025 | RESTAMP - COMMERCIAL v.1 | 04/01/2025 | APPROVED |
| 03/14/2025 | COMMERCIAL REVIEW - LIMITED v.3 | 03/27/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0125-00096
Permit Status: Complete
Permit Description: Coffee Wow Phase 2: Updated equipment and millwork to existing coffee bar.
Installation of new drain manifold serving the coffee bar.
Added dedicated water line and circuit for coffee wow auto clean system.
Add glycol chiller and nitrogen generator for nitro coffee.
| Date | Description | Comments |
|---|---|---|
| 02/27/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0125-00096
Permite Description: Coffee Wow Phase 2: Updated equipment and millwork to existing coffee bar.
Installation of new drain manifold serving the coffee bar.
Added dedicated water line and circuit for coffee wow auto clean system.
Add glycol chiller and nitrogen generator for nitro coffee.
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/08/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 04/08/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 04/08/2025 | ENGR Engineering Final | N/A | Not Applicable | |
| 04/08/2025 | COT - LCME - Mechanical Final | N/A | Not Applicable | |
| 04/08/2025 | COT - LCME - Mechanical Intermediate | N/A | Not Applicable | |
| 04/08/2025 | TRSP - ROW - Final/Close-Out | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0125-00096
Permit Description: Coffee Wow Phase 2: Updated equipment and millwork to existing coffee bar.
Installation of new drain manifold serving the coffee bar.
Added dedicated water line and circuit for coffee wow auto clean system.
Add glycol chiller and nitrogen generator for nitro coffee.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 04/07/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 04/08/2025 | COT - FCON - Fire - Final | Passed | ||
| 04/08/2025 | COT - LCBU - Building Final | Passed | ||
| 04/08/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 04/08/2025 | COT - LCEL - Electrical Final | Passed | ||
| 04/08/2025 | COT - LCEL - Grounding/Bonding | Passed | ||
| 04/08/2025 | COT - LCPL - Plumbing Final | Passed |