Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
01/10/2024
Applicant:
Erin Hastreiter
Description:
new unisex restroom in existing second floor space

Permit Reviews

Permit Number - TC-COM-0124-00054
Permit Status: Issued
Permit Description: new unisex restroom in existing second floor space
Start Date Submittal Complete Date Status  
06/12/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/13/2024 APPROVED Review Details
01/11/2024 COMMERCIAL REVIEW - FULL v.1 02/13/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-0124-00054
Permit Status: Issued
Permit Description: new unisex restroom in existing second floor space
Date Description Comments
02/13/2024 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
01/11/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
02/13/2024 WATER STERILIZATION REPORT IS REQUIRED.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0124-00054
Permit Description: new unisex restroom in existing second floor space
Total Completed Inspections - 16
Date Description Inspector Results Comments
03/13/2024 COT - HCBU - Framing Passed Framing for ADA restroom is complete, plumbing, mechanical, and electrical rough-in are complete. Okay to proceed with drywall installation.
03/13/2024 COT - HCEL - Electrical Above Ceiling Passed Framing for ADA restroom is complete, plumbing, mechanical, and electrical rough-in are complete. Okay to proceed with drywall installation.
03/13/2024 COT - HCPL - Plumbing Above Ceiling Passed Framing for ADA restroom is complete, plumbing, mechanical, and electrical rough-in are complete. Okay to proceed with drywall installation.
03/13/2024 COT - HCPL - Plumbing Intermediate Passed Plumbing rough-in for ADA Restroom is complete and under pressure test for supply water and DWV piping. Okay to proceed with drywall installation.
05/02/2024 COT - FCON - Fire - Final Passed
05/02/2024 COT - FCON - Sprinkler - Final Passed
05/02/2024 ENGR Engineering Final Passed interior to building, instructed to pass inspection by D. Roberts.
05/02/2024 TRSP - ROW - Final/Close-Out Passed
05/03/2024 COT - HCEL - Electrical Final Passed
05/03/2024 COT - HCBU - Building Final Passed
05/03/2024 COT - HCME - Mechanical Final Passed
05/03/2024 COT - HCPL - Plumbing Final Passed
05/24/2024 COT - HCME - Mechanical Intermediate Passed
06/05/2024 COT - HCBU - Building Above Ceiling Passed
06/05/2024 COT - HCEL - Electrical Intermediate Passed
06/05/2024 COT - HCME - Mechanical Above Ceiling Passed

Documents

File Name Document Type  
24F0181_1 TURNERRES 06 10 2024 1649-2024-06-11_V1.PDF DOCUMENTS VIEW
NEW WORLD PLAZA NEW RESTROOM REPORT C BUILDING 6-24_V1.PDF DOCUMENTS VIEW
24F0181_1 TURNERRES 06 10 2024 1649-2024-06-11_V1.PDF DOCUMENTS VIEW
NEW WORLD PLAZA NEW RESTROOM REPORT C BUILDING 6-24_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-1_PLAN SET_V1.PDF DOCUMENTS VIEW
STANTEC-PSA_V1.PDF DOCUMENTS VIEW