Permit: TC-COM-0124-00014
Permit Details
Apply Date:
01/03/2024
Applicant:
Andrew Diller
Description:
new ground up tunnel car wash
Permit Reviews
Permit Number - TC-COM-0124-00014
Permit Status: Complete
Permit Description: new ground up tunnel car wash
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/30/2024 | COMMERCIAL REVIEW - FULL v.3 | 05/30/2024 | REQUIRES RESUBMIT |
| 02/10/2026 | SPECIAL INSPECTION REVIEW v.1 | 02/12/2026 | REQUIRES RESUBMIT |
| 12/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/30/2025 | REQUIRES RESUBMIT |
| 01/07/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 01/12/2026 | APPROVED |
| 06/23/2025 | COMMERCIAL REVIEW - FULL v.1 | 07/18/2025 | REQUIRES RESUBMIT |
| 08/25/2025 | RESTAMP - COMMERCIAL v.1 | 08/27/2025 | APPROVED |
| 01/05/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/01/2024 | REQUIRES RESUBMIT |
| 07/29/2025 | COMMERCIAL REVIEW - FULL v.2 | 08/04/2025 | REQUIRES RESUBMIT |
| 02/18/2026 | SPECIAL INSPECTION REVIEW v.2 | 02/20/2026 | APPROVED |
| 12/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/23/2025 | REQUIRES RESUBMIT |
| 03/13/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/12/2024 | REQUIRES RESUBMIT |
| 12/12/2024 | COMMERCIAL REVIEW - FULL v.5 | 01/08/2025 | APPROVED |
| 05/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/27/2025 | APPROVED |
| 06/12/2024 | COMMERCIAL REVIEW - FULL v.4 | 07/08/2024 | REQUIRES RESUBMIT |
| 06/06/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/16/2025 | APPROVED |
| 01/28/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/02/2026 | APPROVED |
| 01/08/2025 | RESTAMP - COMMERCIAL v.1 | 01/10/2025 | APPROVED |
| 08/20/2025 | COMMERCIAL REVIEW - FULL v.3 | 08/25/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0124-00014
Permit Status: Complete
Permit Description: new ground up tunnel car wash
| Date | Description | Comments |
|---|---|---|
| 05/10/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 05/10/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 01/05/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/06/2025 | COT Department of Transportation and Mobility Authorization to bore under Oracle Rd for proposed public sewer connection. | |
| 05/10/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 05/10/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 02/06/2025 | ||
| 05/10/2024 | Masonry Inspection Report submittal review is required. | |
| 05/10/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 02/01/2024 | Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Lucinda.Hyatt@pima.gov for review and assessment. | |
| 01/05/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/10/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/10/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 02/01/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0124-00014
Permite Description: new ground up tunnel car wash
Total Outstanding Inspections - 18
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2025 | COT - HCBU - Masonry Pregrout | N/A | Deferred | |
| 07/03/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | |
| 08/25/2025 | COT - HCBU - Preslab | N/A | Partial Pass | |
| 12/22/2025 | ENGR Engineering Final | N/A | Partial Pass | contractor needs to submit the stabilization water report. Landscaping is not completed |
| 12/22/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 12/22/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 10/17/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | |
| 12/18/2025 | COT - HCEL - Grounding/Bonding | N/A | Not Ready | |
| 12/18/2025 | COT - HCEL - Outdoor Lighting | N/A | Not Ready | |
| 12/01/2025 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | back of house ok to proceed |
| 12/18/2025 | COT - HCME - Mechanical Final | N/A | Partial Pass | |
| 12/01/2025 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | |
| 12/18/2025 | COT - HCPL - Plumbing Final | N/A | Not Ready | |
| 10/27/2025 | COT - HCPL - Sewer | N/A | Partial Pass | Three retention/filtration tanks are in place. Ok to cover progress area and connect to main sewer system. |
| 12/03/2025 | COT - HCPL - Rough Soil | N/A | Partial Pass | |
| 10/13/2025 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | office area |
| 01/21/2026 | COT - HCEL - Electrical Progress | N/A | Not Applicable | |
| 01/21/2026 | COT - HCME - Mechanical Progress | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0124-00014
Permit Description: new ground up tunnel car wash
Total Completed Inspections - 27