Permit: TC-COM-0123-00550
Permit Details
Apply Date:
01/30/2023
Applicant:
Description:
NEW GROUND-UP SHELL BUILDING. ALL SITE CONDITIONS PER DEVELOPMENT PLAN
Permit Reviews
Permit Number - TC-COM-0123-00550
Permit Status: Complete
Permit Description: NEW GROUND-UP SHELL BUILDING. ALL SITE CONDITIONS PER DEVELOPMENT PLAN
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/13/2023 | REQUIRES RESUBMIT |
| 05/01/2023 | COMMERCIAL REVIEW - FULL v.3 | 05/05/2023 | REQUIRES RESUBMIT |
| 05/12/2023 | COMMERCIAL REVIEW - FULL v.4 | 05/17/2023 | APPROVED |
| 04/06/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/26/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0123-00550
Permit Status: Complete
Permit Description: NEW GROUND-UP SHELL BUILDING. ALL SITE CONDITIONS PER DEVELOPMENT PLAN
| Date | Description | Comments |
|---|---|---|
| 05/17/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 09/20/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 05/17/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 09/20/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 03/28/2023 | Prior to project being finalized applicant must provide recorded abandonment documents for DP22-0241 | |
| 09/20/2024 | Prior to project being finalized applicant must provide recorded abandonment documents for DP22-0241 |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00550
Permite Description: NEW GROUND-UP SHELL BUILDING. ALL SITE CONDITIONS PER DEVELOPMENT PLAN
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | |
| 06/21/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 6-21-23: Conduit on North side for com. |
| 05/01/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 05/01/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
| 05/01/2024 | COT - HCPL - Backwater Valve | N/A | Not Applicable | |
| 03/18/2024 | COT - HCBU - Masonry Pregrout | N/A | Canceled | |
| 03/07/2024 | TRSP - ROW - Final/Close-Out | N/A | Re-inspection required | Visited site found TC was improper and not to MUTCD sent info to Dan Rorertson to havr area inspector contact the contractor and barricade co. to remedy issue. |
| 06/26/2023 | COT - HCEL - Electrical Progress | N/A | Not Ready | |
| 07/11/2023 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 7/6/23: grease inceptor leaking at fitting on north end. 7/11/23: grease inceptor approved to cover. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00550
Permit Description: NEW GROUND-UP SHELL BUILDING. ALL SITE CONDITIONS PER DEVELOPMENT PLAN
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/14/2023 | COT - HCBU - Roof Nailing | Passed | Main roof only; crickets and porch remain. 9/11/23: crickets on main roof. 9/14/23: cricket on west side low roof, tiles roof on west and north sides. Approved to cover. |
|
| 09/20/2023 | COT - HCPL - Sewer | Passed | ||
| 09/20/2023 | COT - HCBU - Framing | Passed | For shell. | |
| 09/22/2023 | COT - HCPL - Plumbing Intermediate | Passed | Main water line. | |
| 10/16/2023 | COT - HCBU - Building Progress | Passed | 10/10/23: Not ready for lath inspection. Seal all penetrations and complete lath. 10/16/23: lath approved. |
|
| 12/06/2023 | COT - HCPL - Plumbing Roof Drains | Passed | 12/6/23: roof drains under test and per plan ok to proceed. | |
| 01/23/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 03/04/2024 | COT - HCBU - Preslab | Passed | ||
| 04/12/2024 | COT - HCEL - Electrical Underground | Passed | 4/12/24: Conduit on west side of building for pole lights and transformer okay to backfill and compact soil. | |
| 05/01/2024 | BULD - Electrical Clearance | Passed | Units 101, 121, 141, 161, and HP. | |
| 05/01/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 05/01/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 05/01/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 05/01/2024 | COT - HCME - Mechanical Progress | Passed | ||
| 05/01/2024 | COT - HCME - Mechanical Final | Passed | ||
| 05/01/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 07/16/2024 | COT - HCBU - TCO | Passed | ||
| 07/23/2024 | COT - FCON - Alarm - Final | Passed | ||
| 07/23/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 07/23/2024 | COT - FCON - Fire - Final | Passed | ||
| 12/06/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
| 12/03/2024 | ENGR Engineering Final | Passed | ||
| 12/04/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 12/04/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
| 12/04/2024 | COT - HCEL - Electrical Progress | Passed | ||
| 12/04/2024 | COT - HCPL - Plumbing Progress | Passed | ||
| 12/04/2024 | COT - HCBU - Building Final | Passed | ||
| 12/06/2024 | COT - HCEL - Electrical Final | Passed |