Permit: TC-COM-0123-00503
Permit Details
Apply Date:
11/21/2022
Applicant:
David Shambach
Description:
New Detached Canopy into a Pizzeria. This addition was originally included in Applicants TI description on TC-COM-1122-00155
Permit Reviews
Permit Number - TC-COM-0123-00503
Permit Status: In review
Permit Description: New Detached Canopy into a Pizzeria. This addition was originally included in Applicants TI description on TC-COM-1122-00155
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.5 | 11/19/2024 | REQUIRES RESUBMIT |
10/30/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 10/30/2024 | REQUIRES RESUBMIT |
10/08/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/08/2024 | REQUIRES RESUBMIT |
03/10/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/10/2023 | APPROVED |
11/04/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.4 | 11/05/2024 | REQUIRES RESUBMIT |
01/18/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/02/2023 | REQUIRES RESUBMIT |
10/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/10/2024 | REQUIRES RESUBMIT |
11/20/2024 | COMMERCIAL REVIEW - FULL v.1 | N/A | IN REVIEW |
Outstanding Activity Conditions
Permit Number - TC-COM-0123-00503
Permit Status: In review
Permit Description: New Detached Canopy into a Pizzeria. This addition was originally included in Applicants TI description on TC-COM-1122-00155
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
02/01/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
02/01/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
Conditions
Permit Number - TC-COM-0123-00503
Permit Status: In review
Permit Description: New Detached Canopy into a Pizzeria. This addition was originally included in Applicants TI description on TC-COM-1122-00155
Date | Description | Comments |
---|---|---|
03/10/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
02/01/2023 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
02/01/2023 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. | |
02/01/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Completed Inspections
Permit Status: In Review
Permit Number: TC-COM-0123-00503
Permit Description: New Detached Canopy into a Pizzeria. This addition was originally included in Applicants TI description on TC-COM-1122-00155
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/11/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
06/14/2023 | COT - HCEL - Electrical Underground | Passed | Ok to cover progress areas. | |
12/01/2023 | COT - HCEL - Electrical Intermediate | Passed | ok for drywall | |
04/22/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
09/10/2024 | COT - HCPL - Rough Soil | Passed | ||
09/10/2024 | BULD - Electrical Clearance | Passed | No clearance required; electric service,is operational. | |
09/10/2024 | COT - BULD - SWG Clearance | Passed | No clearance required; gas service is operational. | |
09/10/2024 | COT - HCBU - Building Final | Passed | ||
09/10/2024 | COT - HCBU - Framing | Passed | ||
09/10/2024 | COT - HCBU - Roof Nailing | Passed | ||
09/10/2024 | COT - HCEL - Electrical Final | Passed | ||
09/10/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
09/10/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
09/10/2024 | COT - HCPL - Plumbing Final | Passed | ||
09/10/2024 | COT - HCPL - Yard Water Line | Passed | ||
09/10/2024 | COT - FCON - Fire - Final | Passed | ||
11/04/2024 | SITE - Zoning Final | Passed |