Permit: T99CM06002
Permit Details
Apply Date:
12/29/1999
Applicant:
BARRIO DEVELOPMENT ,
Description:
TI:APARTMENTS:ADDITION SITE T99CM02073
Contractors:
- BARRIO DEVELOPMENT ,
Completed Inspections
Permit Status: Final
Permit Number: T99CM06002
Permit Description: TI:APARTMENTS:ADDITION SITE T99CM02073
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/11/2000 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection 0000* OK UNDER SLAB #600 |
08/28/2000 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0000* |
11/15/2000 | REINFORCED MASONRY PRE-GROUT | AMATHIES | Approved | IVRS - Inspection 0000* |
03/22/2001 | ROOF NAILING | DWITT | Approved | IVRS - Inspection 0000* |
06/27/2001 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000* |
06/27/2001 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000*1.) PLUMBING ABOVE CEILING OK 2.) ABS DWV OK 3.) COOPER AND PEX PIPING OK PRESSURE TEST OK 4.) CLOSET FLANGES OK 5.) TUBS OK 6.) YARDWATER OK FROM BLDG TO METER LOCATIONS (9TIMES) NEED TO SEE FINAL PIPING AND CONNECTION TO METER. 7.) OK TO COVER WALLS OK 8.) OK TO BACKFILL YARDWATER |
06/28/2001 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000*1.) FINAL PIPING AND CONNECTIONS TO METER OK PRESSURE TEST OK 2.) PLEASE WRAP OR OTHERWISE ISOLATE COPPER FROM TOUCHING OTHER COPPER, FOR PROTECTION AGAINST ELECTROLYSIS. |
07/26/2001 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000* |
07/31/2001 | ELECTRIC - ABOVE CEILING | RMAJUTA | Approved | IVRS - Inspection 0000*INSTALL FLEX ON WH TO SHUT ROCK & ATTACH TO STUD. |
07/31/2001 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | IVRS - Inspection 0000* |
08/02/2001 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* |
08/24/2001 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
08/24/2001 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection 0000* |
01/25/2002 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
02/20/2002 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
02/20/2002 | ENGINEERING - FINAL | DROBERTS | Approved | |
02/20/2002 | FIRE - FINAL | LTHOMAS | Approved | |
02/20/2002 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000*1.) RPBP & EXPANSION TANKS DELETION APPROVED. 2.) ALL CORRECTIONS MADE OK 3.) PLUMBING FINAL OK 4.) OK FOR C OF O PENDING ANY OTHER INSPECTIONS. |
02/20/2002 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection 0000* |
02/20/2002 | ELECTRIC - FINAL | JORTA | Approved | IVRS - Inspection 0000* |
02/21/2002 | PERMIT FINALED | LHANLY | Approved | |
02/21/2002 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection 0000* |