Permit: T99CM04359
Permit Details
Apply Date:
09/10/1999
Applicant:
CAVALLINO CONSTRUCTION
Description:
TRIPLEX:TD#14-41-20
Contractors:
- CAVALLINO CONSTRUCTION
Completed Inspections
Permit Status: Final
Permit Number: T99CM04359
Permit Description: TRIPLEX:TD#14-41-20
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/1999 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | ADDTL COMMS - 1. SOIL WATER TEST OK 2. SITE SEWER WATER TEST OK 3. YARD WATER LINE OK 4. HCS CONNECTION OK 5. OK TO BACKFILL TRENCH |
| 09/30/1999 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | IVRS - Inspection 0000* |
| 09/30/1999 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | ADDTL COMMS - 1. SOIL WATER TEST OK 2. SITE SEWER WATER TEST OK 3. YARD WATER LINE OK 4. HCS CONNECTION OK 5. OK TO BACKFILL TRENCH |
| 09/30/1999 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | ADDTL COMMS - 1. SOIL WATER TEST OK 2. SITE SEWER WATER TEST OK 3. YARD WATER LINE OK 4. HCS CONNECTION OK 5. OK TO BACKFILL TRENCH |
| 12/07/1999 | ELECTRIC - CABLE DROP | KBOLLE | Approved | IVRS - Inspection 0000* |
| 12/21/1999 | PLUMBING - GAS PRESSURE TEST | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 12/21/1999 | PLUMBING - GAS PRESSURE TEST | JSTANLEY | Approved | ADDTL COMMS - NO TEST ON WATER TEST ON GAS OK |