Completed Inspections
Permit Status: C of o
Permit Number: T99CM00917
Permit Description: SITE:HOTEL 1ST - 3RD FLOORS
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/07/1999 | PLUMBING - ROUGH, SOIL | TVALENCI | Approved | IVRS - Inspection 0000* |
09/09/1999 | ELECTRIC - UFER | RSUBA | Approved | IVRS - Inspection 0999* |
12/01/1999 | ROOF NAILING | DWITT | Approved | ADDTL COMMS - CONFIRM 8D @6 O.C. TO BLOCKING PER 10/S4.2. PROVIDE LETTER FROM ENGINEER OF RECORD RE: USE OF OSB VS PSI PER GEN. STRUC. NOTE, WOOD FRAMING NOTES #19 |
12/10/1999 | PLUMBING - SEWER HCS CONNECT | DWITT | Approved | TOP OUT |
12/10/1999 | PLUMBING - SEWER HCS CONNECT | DWITT | Approved | ADDTL COMMS - TOP OUT. |
12/13/1999 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000* |
12/13/1999 | PLUMBING - INTERMEDIATE | TVALENCI | Approved | PARTIAL APPROVAL |
12/13/1999 | PLUMBING - INTERMEDIATE | TVALENCI | Approved | ADDTL COMMS - OK WASTE AND VENT 1ST 2ND FL GROUP ONE THRU GROUP 8. |
12/21/1999 | PLUMBING - GAS PRESSURE TEST | TVALENCI | Approved | IVRS - Inspection 0000* |
12/21/1999 | PLUMBING - GAS PRESSURE TEST | TVALENCI | Approved | ADDTL COMMS - NEED TO SEE MARKING ON ALL GS PIPING GAS PIPING TO DRYER COVER UP NOT A COMPLETE INSPECTION. |
12/22/1999 | ELECTRIC - INTERMEDIATE | JORTA | Approved | IVRS - Inspection 0000* |
12/22/1999 | ELECTRIC - INTERMEDIATE | JORTA | Approved | ADDTL COMMS - 1ST FLOOR ROUGH IN APPROVED IN CLUDED PANELS AND 2ND FLOOR ROUGH COMPLETE. |
12/28/1999 | PLUMBING - ABOVE CEILING | TVALENCI | Approved | IVRS - Inspection 0000* |
12/28/1999 | SHEET ROCK NAILING | DWITT | Approved | AS NOTED |
12/28/1999 | FRAMING | DWITT | Approved | AS NOTED |
12/30/1999 | PLUMBING - YARD WTR LINE/TEST | SLONG | Approved | REJ SILVER BRAZE 3" H2O |
12/30/1999 | PLUMBING - YARD WTR LINE/TEST | SLONG | Approved | ADDTL COMMS - 3 TYPE K COPPER CHECK W/ARCHITECT FOR POSSIBLE THRUST BLOCKING SUGGEST CLEANING UP BRAZED JOINTS. |
02/09/2000 | BOILER ROUGH | RLOHRMAN | Approved | |
02/25/2000 | FIRE - HYDRANTS | FIRE | Approved | |
02/25/2000 | FIRE SPKLR - UG PIPING FLUSH | FIRE | Approved | |
02/25/2000 | FIRE SPKLR - UG, PIPING, HYDRO | FIRE | Approved | |
02/29/2000 | PLUMBING - FINAL | TVALENCI | Approved | IVRS - Inspection 0000* |
05/26/2000 | PERMIT FINALED | DWITT | Approved |