Permit: T98CM00206
Permit Details
Apply Date:
01/16/1998
Applicant:
LANDRUM DAVID
Description:
ADDITION:BEDROOMS & BATHS
Completed Inspections
Permit Status: Final
Permit Number: T98CM00206
Permit Description: ADDITION:BEDROOMS & BATHS
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/1998 | EXCAVATION/LAYOUT REBAR & ZON | FBRUNING | Approved | ADDTL COMMS - 1. KEEP 3 CLEARANCE FORM EARTH TO REBAR. 2. WRAP PLUMBING PRIOR TO POUR. |
| 11/09/1998 | ROOF NAILING | MCAPISTR | Approved | ADDTL COMMS - THE TJI TRUSSES MUST BE CLIPPED TO THE TOP PLATES EVERY ONE. SEE THE TJI CATALOG OR INSTRUCTION SHEET FOR DETAIL OF REINFORCING BLOCK WHICH MUST BE NAILED ON THE SIDE OF THE TJI WEB ( WEB STIFFNER). THE LONG TAB OF THE A2.5 CLIP WILL NAIL TO THE TOP PLATES. THE INTERIOR BEARING WALLS WILL REQUIRE 1/2 ANCHOR BOLTS OR RED HEAD ANCHORS WITHIN 12 OF END AND NOT FURTHER APART THAN 6 FEET. |