Permit: T85CM00001
Permit Details
Apply Date:
01/01/1998
Applicant:
Description:
IF YOU RECEIVE A REQUEST FOR THIS DO NOT DO AN INSPECTION. THIS IS NOT A REAL PERMIT. IT IS A PERM
Outstanding Activity Conditions
Permit Number - T85CM00001
Permit Status: Issued
Permit Description: IF YOU RECEIVE A REQUEST FOR THIS DO NOT DO AN INSPECTION. THIS IS NOT A REAL PERMIT. IT IS A PERM
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
01/30/2006 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
02/17/2006 | SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. |
09/22/2006 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Conditions
Permit Number - T85CM00001
Permit Status: Issued
Permit Description: IF YOU RECEIVE A REQUEST FOR THIS DO NOT DO AN INSPECTION. THIS IS NOT A REAL PERMIT. IT IS A PERM
Date | Description | Comments |
---|---|---|
04/29/2005 | SPECIAL INSPECTION FOR SPECIAL MOMENT-RESISTING CONCRETE FRAME IS REQUIRED. | |
02/17/2006 | FINAL ELEVATION CERTIFICATE REQUIRED: AN ORIGINAL FINAL ELEVATION CERTIFICATE SEALED BY A REGISTERED LAND SURVEYOR IS REQ'D. MAIL ELEVATION CERTIFICATE TO: CITY OF TUCSON, PLANNING & DEVELOPMENT SERVICES DEPT, ATTN: LOREN MAKUS, P.O. BOX 27210, TUCSON, AZ 85726-7210 OR DELIVER IT TO THE 1ST FL NORTH SIDE OF 201 N. STONE AVE. THIS CONDITION APPLIES TO ALL FINAL INSPECTIONS (1090, 2090, 3090, 4090) AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T85CM00001
Permite Description: IF YOU RECEIVE A REQUEST FOR THIS DO NOT DO AN INSPECTION. THIS IS NOT A REAL PERMIT. IT IS A PERM
Total Outstanding Inspections - 34
Completed Inspections
Permit Status: Issued
Permit Number: T85CM00001
Permit Description: IF YOU RECEIVE A REQUEST FOR THIS DO NOT DO AN INSPECTION. THIS IS NOT A REAL PERMIT. IT IS A PERM
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/15/2016 | COT - LCBU - Sustainability | Passed | {Activity date: 01/15/2016; Status: Approved; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection :*} | |
12/08/2016 | COT - LCBU - Stem Wall/Retaining Wall | Passed | {Activity date: 12/08/2016; Status: Approved; Inspector: BSTEVENS; Comment: Entered by ARUIZ1 - } ; {Activity date: 11/24/2015; Status: Not ready for Inspection; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection :*} | |
12/08/2016 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 12/08/2016; Status: Approved; Inspector: BSTEVENS; Comment: Entered by ARUIZ1 - } ; {Activity date: 06/08/2016; Status: Denied; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection : See detailed listing on site.| 999 *} ; {Activity date: 11/24/2015; Status: Partial Approval; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection :*} |
|
12/08/2016 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 12/08/2016; Status: Approved; Inspector: BSTEVENS; Comment: Entered by ARUIZ1 - } ; {Activity date: 09/17/2009; Status: Denied; Inspector: test; Comment: Entered by SDISHRO1 - dfasfdsafdsa} | |
12/08/2016 | COT - LCBU - Roof Nailing | Passed | {Activity date: 12/08/2016; Status: Approved; Inspector: BSTEVENS; Comment: Entered by ARUIZ1 - } ; {Activity date: 08/09/2011; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 04/04/2007; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 03/31/2007; Status: Denied; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - Inspection : The footings and forms are not per code.| 120*} ; {Activity date: 04/03/2007; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} |
|
12/08/2016 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 12/08/2016; Status: Approved; Inspector: BSTEVENS; Comment: Entered by ARUIZ1 - } ; {Activity date: 09/17/2009; Status: Partial Approval; Inspector: test; Comment: Entered by SDISHRO1 - testing} ; {Activity date: 02/25/2009; Status: Partial Approval; Inspector: TEST; Comment: Entered by TEST - IVRS - Inspection :*} ; {Activity date: 02/21/2008; Status: Denied; Inspector: test; Comment: Entered by SDISHRO1 - } | |
10/20/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 09/17/2009; Status: Denied; Inspector: TEST; Comment: Entered by SDISHRO1 - } | |
10/20/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 03/18/2010; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
10/20/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCBU - Framing | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 11/24/2015; Status: Partial Approval; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection :*} | |
10/20/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 03/13/2010; Status: Partial Approval; Inspector: MHENSON; Comment: Entered by MHENSON - IVRS - Inspection :*} | |
10/20/2022 | COT - LCME - Mechanical Final | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCME - Mechanical Progress | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 03/13/2010; Status: Denied; Inspector: MHENSON; Comment: Entered by MHENSON - IVRS - Inspection : See detailed listing on site.| 999*} ; {Activity date: 03/17/2010; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} |
|
10/20/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCBU - Preslab | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - HCBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCEL - Temporary Service | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 06/08/2016; Status: Denied; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection : The commercial hood is not per code.| 420 *} ; {Activity date: 06/03/2016; Status: Denied; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection : No Description.| 420 *} ; {Activity date: 05/27/2016; Status: Denied; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection : The commercial hood is not per code.| 420 *} |
|
10/20/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 12/17/2015; Status: Partial Approval; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection :*} ; {Activity date: 03/31/2015; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 03/18/2010; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 03/13/2010; Status: Partial Approval; Inspector: MHENSON; Comment: Entered by MHENSON - IVRS - Inspection :*} ; {Activity date: 11/16/2009; Status: Partial Approval; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - Inspection :*} ; {Activity date: 06/08/2009; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
10/20/2022 | COT - LCPL - Plumbing Final | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} | |
10/20/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 11/24/2015; Status: Partial Approval; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection :*} | |
10/20/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. No inspection required as per instructions.} ; {Activity date: 05/27/2016; Status: Denied; Inspector: ARUIZ; Comment: Entered by ARUIZ - IVRS - Inspection : See detailed listing on site.| 999 *} |