Permit: T22RW03360
Permit Details
Apply Date:
09/15/2022
Applicant:
Description:
N.957871 C - BORING AND/OR TRENCHING 1650' TO PLACE NEW CTL CABINET, PLUS OTHER BURIED SECTIONS. ALONG WITH 4263' OF AERIAL OVER-LASH AND PLACEMENT.
Permit Reviews
Permit Number - T22RW03360
Permit Status: Complete
Permit Description: N.957871 C - BORING AND/OR TRENCHING 1650' TO PLACE NEW CTL CABINET, PLUS OTHER BURIED SECTIONS. ALONG WITH 4263' OF AERIAL OVER-LASH AND PLACEMENT.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/29/2022 | RIGHT-OF-WAY REVIEW v.3 | 12/29/2022 | APPROVED |
| 11/28/2022 | RIGHT-OF-WAY REVIEW v.1 | 11/29/2022 | REQUIRES RESUBMIT |
| 11/29/2022 | RIGHT-OF-WAY REVIEW v.2 | 12/29/2022 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22RW03360
Permit Status: Complete
Permit Description: N.957871 C - BORING AND/OR TRENCHING 1650' TO PLACE NEW CTL CABINET, PLUS OTHER BURIED SECTIONS. ALONG WITH 4263' OF AERIAL OVER-LASH AND PLACEMENT.
| Date | Description | Comments |
|---|---|---|
| 12/29/2022 | Pre-construction Meeting | |
| 12/29/2022 | Public Outreach | |
| 12/29/2022 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22RW03360
Permite Description: N.957871 C - BORING AND/OR TRENCHING 1650' TO PLACE NEW CTL CABINET, PLUS OTHER BURIED SECTIONS. ALONG WITH 4263' OF AERIAL OVER-LASH AND PLACEMENT.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/19/2023 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | N/A | Re-inspection required | No activity |
| 03/22/2023 | TRSP - ROW - Recurring | N/A | Re-inspection required | Met with Robert from Pauly Construction went asphalt restoration and surface treatment. |
Completed Inspections
Permit Status: Complete
Permit Number: T22RW03360
Permit Description: N.957871 C - BORING AND/OR TRENCHING 1650' TO PLACE NEW CTL CABINET, PLUS OTHER BURIED SECTIONS. ALONG WITH 4263' OF AERIAL OVER-LASH AND PLACEMENT.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/05/2023 | TRSP - ROW - Final/Close-Out | Passed | work appears to be completed |