Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
900 E 12TH ST
Address NEW:
900 E 12TH ST
Apply Date:
06/15/2022
Applicant:
Description:
Cox to start at the TEP pole on the northwest side of 900 E 12th ST begin overlash of 236' heading e; Work Order: PRJ222617-1

Completed Inspections

Permit Status: Complete
Permit Number: T22RW02169
Permit Description: Cox to start at the TEP pole on the northwest side of 900 E 12th ST begin overlash of 236' heading e; Work Order: PRJ222617-1
Total Completed Inspections - 3
Date Description Inspector Results Comments
04/28/2023 TRSP - ROW - Final/Close-Out Passed
04/28/2023 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
04/28/2023 TRSP - ROW - Recurring Passed