Apply Date:
02/01/2022
Applicant:
DURAZO CONSTRUCTION CORP
Description:
Install new water line on 1st. Trench 75’L X 2’W X 3’D on north side of 1st between curb and sidewalk then under sidewalk and into the park. No sidewalk will be removed. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. IN THE EVENT THAT WEEKEND OR AFTER-HOURS WORK IS INTENDED, CONTACT COT INSPECTION STAFF. DAN ROBERTSON AT 520-400-6722 OR TOM ADKINS AT 520-400-3813. After the fact permit - Any legal questions related to this work shall be directed to Durazo Construction Corp to address since DTM did not have an opportunity to review, approve or inspect work.
Completed Inspections
Permit Status: Final
Permit Number: T22RW00321
Permit Description: Install new water line on 1st. Trench 75’L X 2’W X 3’D on north side of 1st between curb and sidewalk then under sidewalk and into the park. No sidewalk will be removed.
** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
IN THE EVENT THAT WEEKEND OR AFTER-HOURS WORK IS INTENDED, CONTACT COT INSPECTION STAFF. DAN ROBERTSON AT 520-400-6722 OR TOM ADKINS AT 520-400-3813.
After the fact permit - Any legal questions related to this work shall be directed to Durazo Construction Corp to address since DTM did not have an opportunity to review, approve or inspect work.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/20/2022 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | all work completed after the fact. no issues |