Permit: T22CM08158
Permit Details
Apply Date:
10/20/2022
Applicant:
Kyle Hough
Description:
TI: Office for Hearing Care
Permit Reviews
Permit Number - T22CM08158
Permit Status: Complete
Permit Description: TI: Office for Hearing Care
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/20/2022 | COMMERCIAL - TI | 10/20/2022 | ACTIVE |
04/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/03/2023 | REQUIRES RESUBMIT |
05/09/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 05/09/2023 | APPROVED |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/05/2022 | REQUIRES RESUBMIT |
12/19/2022 | COMMERCIAL REVIEW - FULL v.2 | 02/07/2023 | APPROVED |
Conditions
Permit Number - T22CM08158
Permit Status: Complete
Permit Description: TI: Office for Hearing Care
Date | Description | Comments |
---|---|---|
12/05/2022 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM08158
Permite Description: TI: Office for Hearing Care
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/19/2023 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 4-19-23: Address for suite is 7035, tenant in 7033 is taking over this space as well. Laundry sink plumbing is complete. Gas water heater is being installed on new raised platform. |
06/05/2023 | COT - LCPL - Plumbing Roof Drains | N/A | Not Applicable | Scheduled to view inspection history. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM08158
Permit Description: TI: Office for Hearing Care
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/02/2023 | COT - LCBU - Framing | Passed | ||
03/02/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
03/02/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
03/20/2023 | COT - HCPL - Rough Soil | Passed | ||
04/21/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
05/24/2023 | COT - BULD - SWG Clearance | Passed | ||
05/24/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
06/09/2023 | COT - FCON - Fire - Final | Passed | ||
06/09/2023 | COT - LCME - Mechanical Final | Passed | ||
06/09/2023 | COT - HCME - Mechanical Final | Passed | ||
06/09/2023 | COT - FCON - Sprinkler - Final | Passed | ||
06/12/2023 | COT - LCPL - Plumbing Final | Passed | ||
06/12/2023 | COT - LCBU - Building Final | Passed | ||
06/12/2023 | COT - LCEL - Electrical Final | Passed |