Permit: T22CM08014
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
1645 W VALENCIA RD 111
Address NEW:
1645 W VALENCIA RD 111
Apply Date:
10/18/2022
Applicant:
Jose Quintero
Description:
TI: Restaurant
Permit Reviews
Permit Number - T22CM08014
Permit Status: Issued
Permit Description: TI: Restaurant
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/18/2022 | COMMERCIAL - TI | 10/19/2022 | ACTIVE |
| 10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/04/2023 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM08014
Permite Description: TI: Restaurant
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/09/2023 | COT - HCBU - Framing | N/A | Not Ready | doors locked, no access |
| 04/28/2023 | COT - FCON - Sprinkler - Final | N/A | Not Applicable | No sprinkler was done. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM08014
Permit Description: TI: Restaurant
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/15/2023 | COT - HCBU - Framing | Passed | Framing for new bar is complete. Okay to sheet rock with green board and vinyl wall covering. | |
| 02/15/2023 | COT - HCPL - Plumbing Intermediate | Passed | Rough-in of plumbing pipes is complete. Okay to cover with sheet rock. | |
| 02/15/2023 | COT - HCPL - Rough Soil | Passed | Underground plumbing pipes are holding water. Okay to backfill trench and re-pour concrete floor. | |
| 02/15/2023 | COT - HCEL - Electrical Above Ceiling | Passed | conduit and boxes are properly supported. Boxes are labeled with the correct circuit number. Okay to close up ceiling. | |
| 02/15/2023 | COT - HCEL - Electrical Intermediate | Passed | Electrical rough-in is complete. Boxes, conduit and electrical wires are properly installed. Okay to cover with sheet rock. | |
| 04/28/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
| 04/28/2023 | COT - HCME - Mechanical Final | Passed | A/C units, ductwork, and thermostat are installed and operational. | |
| 04/28/2023 | COT - HCEL - Electrical Final | Passed | Electrical panels are properly marked, GFCI receptacles are installed, lights are installed, and kitchen appliances are installed. Everything is operational. | |
| 04/28/2023 | COT - HCPL - Plumbing Final | Passed | Plumbing is complete. | |
| 04/28/2023 | COT - HCBU - Building Final | Passed | Construction is complete. Okay to issue C of O. | |
| 04/28/2023 | COT - FCON - Hood System - Final | Passed | Approved on 2/21/23 on permit # TF-FCP-0123-00295. | |
| 04/28/2023 | COT - HCBU - CofO | Passed | Construction is complete. Okay to issue C of O. |