Permit: T22CM07883
Permit Details
Apply Date:
10/14/2022
Applicant:
Description:
Roof-mounted PV system on Building B: 108 Modules, TEP utility meter 169207093.
Permit Reviews
Permit Number - T22CM07883
Permit Status: Complete
Permit Description: Roof-mounted PV system on Building B: 108 Modules, TEP utility meter 169207093.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/14/2022 | OTHER | 10/20/2022 | ACTIVE |
10/29/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/10/2022 | REQUIRES RESUBMIT |
12/14/2022 | COMMERCIAL REVIEW - FULL v.2 | 01/05/2023 | REQUIRES RESUBMIT |
01/06/2023 | COMMERCIAL REVIEW - FULL v.3 | 01/30/2023 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07883
Permit Description: Roof-mounted PV system on Building B: 108 Modules, TEP utility meter 169207093.
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/15/2023 | SITE - Zoning Final | Passed | ||
03/15/2023 | COT - LCEL - Electrical Final | Passed | Solar | |
03/15/2023 | BULD - Electrical Clearance | Passed | Approved, DGL/DGC Clearance to TEP is required | |
03/15/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
03/15/2023 | COT - LCEL - Electrical Progress | Passed | ||
03/15/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
04/19/2023 | ENGR Engineering Final | Passed |