Permit: T22CM07804
Permit Details
Apply Date:
10/12/2022
Applicant:
Description:
New Building
Permit Reviews
Permit Number - T22CM07804
Permit Status: Complete
Permit Description: New Building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/12/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/12/2022 | ACTIVE |
| 07/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/18/2025 | REQUIRES RESUBMIT |
| 05/25/2023 | COMMERCIAL REVIEW - FULL v.5 | 06/29/2023 | REQUIRES RESUBMIT |
| 07/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 07/24/2025 | REQUIRES RESUBMIT |
| 10/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/07/2025 | APPROVED |
| 12/22/2022 | COMMERCIAL REVIEW - FULL v.2 | 01/17/2023 | REQUIRES RESUBMIT |
| 04/24/2023 | COMMERCIAL REVIEW - FULL v.4 | 05/25/2023 | REQUIRES RESUBMIT |
| 07/25/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 07/25/2025 | REQUIRES RESUBMIT |
| 08/31/2023 | COMMERCIAL REVIEW - FULL v.6 | 09/22/2023 | REQUIRES RESUBMIT |
| 10/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/13/2025 | APPROVED |
| 07/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.4 | 08/01/2025 | APPROVED |
| 02/16/2023 | COMMERCIAL REVIEW - FULL v.3 | 03/15/2023 | REQUIRES RESUBMIT |
| 09/26/2023 | COMMERCIAL REVIEW - FULL v.7 | 10/04/2023 | APPROVED |
| 10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/25/2022 | REQUIRES RESUBMIT |
| 10/23/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/23/2024 | APPROVED |
| 10/04/2023 | RESTAMP - COMMERCIAL v.1 | 10/17/2023 | APPROVED |
Conditions
Permit Number - T22CM07804
Permit Status: Complete
Permit Description: New Building
| Date | Description | Comments |
|---|---|---|
| 10/23/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 10/12/2022 | GENERAL CONTRACTOR LETTER (GCL) REQUIRD PRIOR TO ISSUANCE | |
| 10/23/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 10/23/2024 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
| 10/23/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 10/23/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 09/24/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 10/23/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 08/01/2025 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 10/23/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM07804
Permite Description: New Building
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 7/19/24: electrical in-wall at first floor per plan ok to proceed |
| 05/20/2024 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 2/14/24: reinforcement per plan first lift ok to grout @4ft 3/5/24 2nd lift ok for grout 3/21/24: 3rd lift ok for grout. 5/20/24: 4th lift ok to grout. Reinforcement at site wall per plans ok to proceed. |
| 01/09/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 1/9/24 partial for building exterior footers, interior to go |
| 11/22/2024 | COT - HCBU - Framing | N/A | Partial Pass | 11/22/24: first floor framing passed. |
| 12/17/2024 | COT - HCBU - Building Progress | N/A | Partial Pass | 12/17/24: drywall nailing passed ok to proceed. |
| 11/04/2025 | FCON – Fire – Intermediate | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07804
Permit Description: New Building
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/02/2024 | COT - HCPL - Rough Soil | Passed | 1/25/24: plumbing underground in building per plan ok to back fill. Shading required. 2/2/24: plumbing underground and sewer connection complete. Grease interceptor installed per plans and tested ok to proceed and backfill. |
|
| 02/02/2024 | COT - HCBU - Preslab | Passed | ||
| 08/02/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
| 11/26/2024 | COT - HCPL - Plumbing Intermediate | Passed | OK to insulate and cover walls. | |
| 04/29/2025 | BULD - Electrical Clearance | Passed | 4-29-25, panel is okay to be energized. ECO clearance sent to TEP. | |
| 07/11/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
| 07/11/2025 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 07/11/2025 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 07/11/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 07/11/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 07/22/2025 | COT - BULD - SWG Clearance | Passed | 7/22/25: SWG CLEARANCE APPROVED | |
| 10/08/2025 | COT - HCEL - Electrical Intermediate | Passed | ||
| 10/08/2025 | COT - LCME - Mechanical Progress | Passed | ||
| 10/08/2025 | COT - LCME - Kitchen Hood | Passed | ||
| 10/08/2025 | COT - HCBU - Masonry Pregrout | Passed | ||
| 10/08/2025 | COT - HCPL - Sewer | Passed | ||
| 10/08/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 10/08/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 10/08/2025 | COT - HCBU - Framing | Passed | ||
| 10/08/2025 | COT - HCEL - Electrical Progress | Passed | ||
| 10/08/2025 | COT - LCBU - Building Progress | Passed | ||
| 10/08/2025 | COT - HCEL - Electrical Underground | Passed | ||
| 10/08/2025 | COT - HCPL - Yard Water Line | Passed | ||
| 10/08/2025 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 10/08/2025 | COT - HCBU - Building Progress | Passed | ||
| 10/22/2025 | COT - HCPL - Gas Final | Passed | ||
| 10/31/2025 | COT - LCBU - Building Final | Passed | ||
| 10/22/2025 | COT - LCME - Mechanical Final | Passed | ||
| 10/31/2025 | COT - HCBU - Building Final | Passed | ||
| 10/31/2025 | COT - HCEL - Outdoor Lighting | Passed | ||
| 10/22/2025 | COT - HCEL - Electrical Final | Passed | ||
| 10/28/2025 | COT - FCON - Alarm - Final | Passed | ||
| 10/28/2025 | COT - FCON - Fire - Final | Passed | ||
| 11/03/2025 | ENGR Engineering Final | Passed | ||
| 11/04/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 11/04/2025 | COT - FCON - Hood System - Final | Passed |