Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
10/07/2022
Applicant:
Description:
SFR MERI156021 T21-M0063

Outstanding Activity Conditions

Permit Number - T22CM07731
Permit Status: Issued
Permit Description: SFR MERI156021 T21-M0063
Total Outstanding Activity Conditions - 4
Date Name
10/07/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
10/07/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
10/07/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
10/07/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2021-022/P21WP00211 IS ACCEPTED AND RELEASED BY PCRWRD

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM07731
Permite Description: SFR MERI156021 T21-M0063
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - RSEL - Outdoor Lighting N/A Not Ready
10/27/2022 COT - RSEL - Electrical Final N/A Not Ready
01/23/2023 COT - RSPL - Sewer N/A Partial Pass partial connection to hub set. okay to backfill. shading required
03/27/2023 COT - RSPL - Plumbing Final N/A Not Ready
03/24/2023 ENGR Engineering Final N/A Not Ready Basin still under construction
03/27/2023 COT - RSME - Mechanical Final N/A Not Ready
03/27/2023 RSBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM07731
Permit Description: SFR MERI156021 T21-M0063
Total Completed Inspections - 16
Date Description Inspector Results Comments
01/23/2023 COT - RSPL - Rough Soil Passed okay to backfill. shading required
01/26/2023 COT - RSBU - Preslab Passed
01/26/2023 COT - RSEL - Electrical Underground Passed
01/26/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
02/03/2023 COT - RSBU - Exterior Clips/Sheathing Passed h2.5 clips are installed on all roof trusses. shear bracing is nailed on exterior corners of building. okay to start stucco prep.
02/03/2023 COT - RSBU - Roof Nailing Passed roof sheathing is properly nailed off. Okay to dry-in.
02/13/2023 COT - RSEL - Grounding/Bonding Passed
02/13/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
02/13/2023 COT - RSPL - Gas Pressure Test Passed
02/13/2023 RSME - Mechanical Progress Passed
02/13/2023 COT - LCBU - Framing Passed
02/13/2023 COT - RSEL - Construction Power Passed clearance for TEP ECO.
02/13/2023 COT - LCPL - Plumbing Intermediate Passed
02/24/2023 COT - HCBU - Interior Shear Bracing Passed
03/27/2023 COT - RSPL - Yard Water Line Passed
03/27/2023 COT - BULD - SWG Clearance Passed SWG for meter only

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
PERMIT APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
REV1_PLAN.PDF DOCUMENTS VIEW
REV1_SITE PLAN.PDF DOCUMENTS VIEW
REVISION APPLICATION.PDF DOCUMENTS VIEW
REVISION NARRATIVE.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW