Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
10/06/2022
Applicant:
Kelly Rayman
Description:
SFR DRHOH30M21 T21-M0041

Permit Reviews

Permit Number - T22CM07682
Permit Status: Issued
Permit Description: SFR DRHOH30M21 T21-M0041
Start Date Submittal Complete Date Status  
06/14/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/22/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T22CM07682
Permit Status: Issued
Permit Description: SFR DRHOH30M21 T21-M0041
Total Outstanding Activity Conditions - 2
Date Name
10/06/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
10/06/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2018-112(P21WP00113) IS ACCEPTED ANDRELEASED BY PCRWRD

Conditions

Permit Number - T22CM07682
Permit Status: Issued
Permit Description: SFR DRHOH30M21 T21-M0041
Date Description Comments
10/06/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/21/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/21/2023 Post-Tension Inspection Report is required.
06/21/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM07682
Permite Description: SFR DRHOH30M21 T21-M0041
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
04/27/2023 COT - LCBU - Framing N/A Partial Pass Partial per intermediates. 4/27/2023
04/27/2023 COT - RSEL - Construction Power N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM07682
Permit Description: SFR DRHOH30M21 T21-M0041
Total Completed Inspections - 22
Date Description Inspector Results Comments
03/24/2023 COT - RSPL - Rough Soil Passed
03/24/2023 COT - RSPL - Yard Water Line Passed
03/24/2023 COT - RSPL - Sewer Passed
04/05/2023 COT - RSBU - Preslab Passed okay for concrete placement in slab. 4/5/2023
04/05/2023 COT - RSEL - Electrical Underground Passed
04/05/2023 COT - RSBU - Excavation/Rebar/Zoning Passed okay for concrete placement in slab. 4/5/2023
04/05/2023 COT - RSEL - Grounding/Bonding Passed
04/25/2023 COT - RSBU - Roof Nailing Passed
04/27/2023 COT - RSBU - Exterior Clips/Sheathing Passed Approved. Corrections were made. 4/27/2023
05/11/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/11/2023 COT - LCPL - Plumbing Intermediate Passed
05/11/2023 COT - RSPL - Gas Pressure Test Passed
05/11/2023 RSME - Mechanical Progress Passed
05/24/2023 COT - HCBU - Interior Shear Bracing Passed
06/15/2023 BULD - Electrical Clearance Passed Clearance for TEP ECO. 6/15/2023
08/29/2023 COT - RSPL - Plumbing Final Passed
08/29/2023 ENGR Engineering Final Passed double staked plantings need nursery stake removed. A/C unit needs leveled. paint residue needs removal.
08/29/2023 RSBU - Building Final Passed
08/29/2023 COT - RSME - Mechanical Final Passed
08/29/2023 COT - RSEL - Electrical Final Passed
08/29/2023 COT - RSEL - Outdoor Lighting Passed
08/30/2023 COT - BULD - SWG Clearance Passed

Documents

File Name Document Type  
SVB 32 SIC-2023-06-13_V1.PDF DOCUMENTS VIEW
SVB 32 PT REPORT-2023-06-13_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW