Permit: T22CM07600
Permit Details
Apply Date:
10/04/2022
Applicant:
Description:
INSTALLATION OF 437.88KW ROOFTOP AND CANOPY MOUNTED PV SOLAR SYSTEM
Permit Reviews
Permit Number - T22CM07600
Permit Status: Issued
Permit Description: INSTALLATION OF 437.88KW ROOFTOP AND CANOPY MOUNTED PV SOLAR SYSTEM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/04/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/20/2022 | ACTIVE |
03/03/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/24/2023 | APPROVED |
08/09/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/13/2023 | APPROVED |
08/16/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/20/2024 | APPROVED |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/07/2022 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - T22CM07600
Permit Status: Issued
Permit Description: INSTALLATION OF 437.88KW ROOFTOP AND CANOPY MOUNTED PV SOLAR SYSTEM
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
08/12/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
08/12/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. |
Conditions
Permit Number - T22CM07600
Permit Status: Issued
Permit Description: INSTALLATION OF 437.88KW ROOFTOP AND CANOPY MOUNTED PV SOLAR SYSTEM
Date | Description | Comments |
---|---|---|
08/12/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
08/12/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
08/12/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM07600
Permite Description: INSTALLATION OF 437.88KW ROOFTOP AND CANOPY MOUNTED PV SOLAR SYSTEM
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/28/2023 | COT - LCEL - Electrical Progress | N/A | Not Applicable | |
10/04/2023 | BULD - Electrical Clearance | N/A | Partial Pass | Partial for new neutrals from transformer to service panel, RECN Clearance was called into TEP at 10:45 (powerkill) |
06/27/2023 | COT - LCBU - Building Progress | N/A | Partial Pass | Partial pass. Looked at 6 footings on the southwest side of the complex south to north and 7 footings on the northeast side of complex east to west. Depth as per plans okay for concrete placement. 6/27/2023 |
03/18/2024 | COT - LCBU - Preslab | N/A | Not Applicable | CLOSE PERMIT |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM07600
Permit Description: INSTALLATION OF 437.88KW ROOFTOP AND CANOPY MOUNTED PV SOLAR SYSTEM
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/27/2023 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
10/12/2023 | BULD - Electrical Clearance | Passed | Approved, DGC/DGL Clearance to TEP is required for the solar meter | |
10/12/2023 | COT - LCBU - Building Progress | Passed | ||
10/12/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
10/12/2023 | COT - CSOL - Electrical Final Solar Project | Passed | ||
10/12/2023 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
10/12/2023 | COT - CSOL - Outdoor Lighting Solar Project | Passed | ||
10/12/2023 | COT - LCBU - Building Final | Passed | ||
10/12/2023 | COT - LCEL - Electrical Final | Passed | ||
03/15/2024 | ENGR Engineering Final | Passed | ||
03/15/2024 | SITE - Zoning Final | Passed | ||
03/15/2024 | COT - CSOL - Electrical Underground Solar Project | Passed |