Permit Reviews

Permit Number - T22CM07577
Permit Status: Complete
Permit Description: NEW 890 SF SHELL BUILDING WITH A DRIVE-THRU
Start Date Submittal Complete Date Status  
10/03/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 10/20/2022 ACTIVE Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 11/22/2022 REQUIRES RESUBMIT Review Details
01/09/2023 COMMERCIAL REVIEW - FULL v.2 02/03/2023 APPROVED Review Details
05/25/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/13/2023 APPROVED Review Details
01/17/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/18/2024 APPROVED Review Details

Conditions

Permit Number - T22CM07577
Permit Status: Complete
Permit Description: NEW 890 SF SHELL BUILDING WITH A DRIVE-THRU
Date Description Comments
10/19/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
10/19/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/19/2022 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
02/03/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
01/18/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
01/18/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
01/18/2024 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
01/18/2024 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM07577
Permite Description: NEW 890 SF SHELL BUILDING WITH A DRIVE-THRU
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
COT - FCON - Fire - Final N/A Not Ready
08/08/2023 COT - HCEL - Electrical Underground N/A Partial Pass 5/26/23: rough electric underground stubbed into the building at southeast corner.
8/7/23: partial electrical underground from main panel to secondary, from secondary to light post, menu and signage.
PDSD Building Division Pre-Construction Meeting N/A Requested

Completed Inspections

Permit Status: Complete
Permit Number: T22CM07577
Permit Description: NEW 890 SF SHELL BUILDING WITH A DRIVE-THRU
Total Completed Inspections - 29
Date Description Inspector Results Comments
06/15/2023 COT - HCEL - Grounding/Bonding Passed
07/19/2023 COT - HCBU - Roof Nailing Passed Ok to dry in roof system.
08/04/2023 COT - HCPL - Sewer Passed
08/11/2023 COT - HCEL - Electrical Intermediate Passed Ok to cover interior walls.
08/11/2023 COT - HCPL - Plumbing Intermediate Passed Ok to cover interior walls
10/04/2023 COT - HCBU - Masonry Pregrout Passed To be completed on DP Permit
12/06/2023 COT - HCEL - Electrical Final Passed
12/11/2023 COT - FCON - Fire - Final Passed
12/14/2023 COT - HCME - Mechanical Final Passed
12/14/2023 COT - HCBU - Building Final Passed
12/14/2023 COT - HCPL - Plumbing Final Passed
12/14/2023 BULD - Electrical Clearance Passed Submitted to K.R. at 0955 hours
12/14/2023 COT - HCPL - Yard Water Line Passed
12/14/2023 COT - HCPL - Rough Soil Passed
12/14/2023 COT - LCBU - Building Final Passed
12/14/2023 COT - HCEL - Electrical Underground Passed
12/14/2023 COT - HCBU - Excavation/Rebar/Zoning Passed
12/14/2023 COT - HCBU - Preslab Passed
12/14/2023 COT - HCBU - Building Progress Passed
12/14/2023 COT - HCEL - Electrical Progress Passed
12/14/2023 COT - HCBU - Interior Shear Bracing Passed
12/14/2023 COT - HCEL - Outdoor Lighting Passed
12/14/2023 COT - HCME - Mechanical Intermediate Passed
12/14/2023 COT - HCME - Mechanical Above Ceiling Passed
12/14/2023 COT - HCME - Mechanical Progress Passed
12/14/2023 COT - HCPL - Backwater Valve Passed
12/14/2023 COT - HCPL - Plumbing Progress Passed
12/14/2023 COT - HCPL - Plumbing Roof Drains Passed
01/19/2024 SITE - Zoning Final Passed

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
CITY OF TUCSON SI CERT T22CM07577, STARBUCKS ST. MARY'S - SILVERBELL-2024-01-17_V1.PDF DOCUMENTS VIEW
CITY OF TUCSON SI CERT T22CM07577, STARBUCKS ST. MARY'S - SILVERBELL-2024-01-17_V1.PDF DOCUMENTS VIEW
23-006 12 ROOF TRUSS SUBMITTAL-REVIEWED_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2_STRUCTURAL CALCS_V1.PDF DOCUMENTS VIEW
CONS-2_PLANS_V2.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_COMPLIANCE REPORT_V1.PDF DOCUMENTS VIEW
1_GEOTECHNICAL ENGINEERING REPORT_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERTIFICATE-2022-10-28_V1.PDF DOCUMENTS VIEW
1_STRUCTURAL CALCS_V1.PDF DOCUMENTS VIEW
CONS-1_PLAN SET_V1.PDF DOCUMENTS VIEW
T22CM07577 APPROVED STAMPED_COMPLIANCE REPORT_V1.PDF DOCUMENTS VIEW
T22CM07577 APPROVED STAMPED_GEOTECHNICAL ENGINEERING REPORT_V1.PDF DOCUMENTS VIEW
T22CM07577 APPROVED STAMPED_SPECIAL INSPECTION CERTIFICATE-2022-10-28_V1.PDF DOCUMENTS VIEW
T22CM07577 APPROVED STAMPED_STRUCTURAL CALCS_V1.PDF DOCUMENTS VIEW
T22CM07577 PLAN REVIEW FEE AND INSPECTION SHEET _V1.PDF DOCUMENTS VIEW