Permit Details

Status:
Issued
Type:
Commercial Building
Address NEW:
1715 S RESEARCH LP
Apply Date:
10/03/2022
Applicant:
Alan Romo Lopez
Description:
TI:OFFICE

Permit Reviews

Permit Number - T22CM07559
Permit Status: Issued
Permit Description: TI:OFFICE
Start Date Submittal Complete Date Status  
10/03/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 10/18/2022 ACTIVE Review Details
12/12/2022 COMMERCIAL REVIEW - FULL v.2 02/28/2023 APPROVED Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 11/28/2022 REQUIRES RESUBMIT Review Details
06/02/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/08/2023 APPROVED Review Details
03/14/2023 COMMERCIAL REVIEW - FULL v.1 03/24/2023 APPROVED Review Details

Conditions

Permit Number - T22CM07559
Permit Status: Issued
Permit Description: TI:OFFICE
Date Description Comments
02/11/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
10/03/2022 GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE
02/11/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM07559
Permite Description: TI:OFFICE
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
05/03/2023 COT - HCBU - Building Above Ceiling N/A Not Ready 5/3/23: several electric issues

Completed Inspections

Permit Status: Issued
Permit Number: T22CM07559
Permit Description: TI:OFFICE
Total Completed Inspections - 18
Date Description Inspector Results Comments
03/09/2023 COT - HCPL - Rough Soil Passed
03/28/2023 COT - HCBU - Framing Passed
03/28/2023 COT - HCEL - Electrical Intermediate Passed
03/28/2023 COT - HCME - Mechanical Intermediate Passed
03/28/2023 COT - HCPL - Plumbing Intermediate Passed
04/05/2023 COT - HCPL - Plumbing Above Ceiling Passed
04/05/2023 COT - HCME - Mechanical Above Ceiling Passed
04/05/2023 COT - HCEL - Electrical Above Ceiling Passed
04/11/2023 COT - HCBU - Interior Shear Bracing Passed
05/04/2023 COT - HCBU - Building Above Ceiling Passed
06/08/2023 COT - FCON - Fire - Final Passed
06/08/2023 COT - FCON - Sprinkler - Final Passed
06/08/2023 SITE - Zoning Final Passed
06/08/2023 ENGR Engineering Final Passed
06/08/2023 COT - HCEL - Electrical Final Passed
06/08/2023 COT - HCME - Mechanical Final Passed
06/08/2023 COT - HCPL - Plumbing Final Passed
06/21/2023 COT - HCBU - Building Final Passed