Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM07559
Permit Details
Apply Date:
10/03/2022
Applicant:
Anthony Dao
Description:
TI:OFFICE
Permit Reviews
Permit Number - T22CM07559
Permit Status: Issued
Permit Description: TI:OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/03/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/18/2022 | ACTIVE |
12/12/2022 | COMMERCIAL REVIEW - FULL v.2 | 02/28/2023 | APPROVED |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/28/2022 | REQUIRES RESUBMIT |
06/02/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/08/2023 | APPROVED |
03/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/24/2023 | APPROVED |
Conditions
Permit Number - T22CM07559
Permit Status: Issued
Permit Description: TI:OFFICE
Date | Description | Comments |
---|---|---|
02/11/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
10/03/2022 | GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE | |
02/11/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM07559
Permite Description: TI:OFFICE
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/03/2023 | COT - HCBU - Building Above Ceiling | N/A | Not Ready | 5/3/23: several electric issues |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM07559
Permit Description: TI:OFFICE
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/09/2023 | COT - HCPL - Rough Soil | Passed | ||
03/28/2023 | COT - HCBU - Framing | Passed | ||
03/28/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
03/28/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
03/28/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
04/05/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
04/05/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
04/05/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
04/11/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
05/04/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
06/08/2023 | COT - FCON - Fire - Final | Passed | ||
06/08/2023 | COT - FCON - Sprinkler - Final | Passed | ||
06/08/2023 | SITE - Zoning Final | Passed | ||
06/08/2023 | ENGR Engineering Final | Passed | ||
06/08/2023 | COT - HCEL - Electrical Final | Passed | ||
06/08/2023 | COT - HCME - Mechanical Final | Passed | ||
06/08/2023 | COT - HCPL - Plumbing Final | Passed | ||
06/21/2023 | COT - HCBU - Building Final | Passed |