Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
10/03/2022
Applicant:
MeChell Rentfro
Description:
SFR MER1301460 T21-M0072

Outstanding Activity Conditions

Permit Number - T22CM07543
Permit Status: Issued
Permit Description: SFR MER1301460 T21-M0072
Total Outstanding Activity Conditions - 3
Date Name
10/03/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
10/03/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
10/03/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-095/P22WP00021 IS ACCEPTED AND RELEASED BY PCRWRD

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM07543
Permite Description: SFR MER1301460 T21-M0072
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - RSBU - Exterior Clips/Sheathing N/A Not Ready
10/26/2022 COT - RSBU - Roof Nailing N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM07543
Permit Description: SFR MER1301460 T21-M0072
Total Completed Inspections - 24
Date Description Inspector Results Comments
12/20/2022 COT - RSPL - Rough Soil Passed
12/20/2022 COT - RSPL - Yard Water Line Passed
12/23/2022 COT - RSEL - Grounding/Bonding Passed
12/23/2022 COT - RSEL - Electrical Underground Passed
12/23/2022 COT - RSBU - Preslab Passed
12/23/2022 COT - RSBU - Excavation/Rebar/Zoning Passed
01/13/2023 COT - RSBU - Exterior Clips/Sheathing Passed
01/13/2023 COT - RSBU - Roof Nailing Passed
02/21/2023 BULD - Electrical Clearance Passed TEP ECO
02/21/2023 COT - LCBU - Framing Passed
02/21/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
02/21/2023 COT - RSEL - Construction Power Passed
02/21/2023 COT - RSPL - Gas Pressure Test Passed
02/21/2023 COT - LCPL - Plumbing Intermediate Passed
02/21/2023 RSME - Mechanical Progress Passed
03/16/2023 COT - HCBU - Interior Shear Bracing Passed
05/22/2023 COT - BULD - SWG Clearance Passed 5/22/23: SWG clearance issued.
05/22/2023 COT - RSPL - Sewer Passed
05/22/2023 COT - RSPL - Plumbing Final Passed
06/14/2023 COT - RSME - Mechanical Final Passed Mechanical equipment is installed and operational. A/C registers are installed. Thermostat is installed and operational.
06/14/2023 COT - RSEL - Electrical Final Passed AFCI & GFCI breakers are installed in electrical panel, panel is properly labeled. Electrical outlets and fixtures are installed and operational. Smoke detectors are functioning properly.
06/14/2023 RSBU - Building Final Passed Construction is complete on this house. Plumbing, electrical, and mechanical are all working well. Okay to issue a Certificate of Occupancy.
06/14/2023 COT - RSEL - Outdoor Lighting Passed Outdoor lighting fixtures are installed and operational with the correct size light bulb for wattage.
06/14/2023 ENGR Engineering Final Passed

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW