Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM07539
Permit Details
Apply Date:
10/01/2022
Applicant:
Andrea Flood
Description:
SFR STF40K T20-M0039
Outstanding Activity Conditions
Permit Number - T22CM07539
Permit Status: Issued
Permit Description: SFR STF40K T20-M0039
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
10/01/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
10/01/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM07539
Permite Description: SFR STF40K T20-M0039
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/22/2023 | COT - LCBU - Framing | N/A | Not Ready | |
02/22/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | missing smoke detectors in bedroom and hallway. |
05/18/2023 | COT - RSPL - Plumbing Final | N/A | Partial Pass |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM07539
Permit Description: SFR STF40K T20-M0039
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/13/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/13/2022 | COT - RSPL - Sewer | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/13/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/19/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - RSBU - Preslab | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/23/2023 | COT - RSBU - Roof Nailing | Passed | ||
01/23/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/22/2023 | COT - RSPL - Gas Pressure Test | Passed | holding 15 psi | |
02/22/2023 | COT - RSEL - Construction Power | Passed | clearance for TEP ECO | |
02/22/2023 | RSME - Mechanical Progress | Passed | ||
02/22/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
02/27/2023 | COT - LCBU - Framing | Passed | ||
02/27/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
03/14/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
05/18/2023 | COT - BULD - SWG Clearance | Passed | ||
05/22/2023 | COT - RSPL - Plumbing Final | Passed | ||
05/22/2023 | ENGR Engineering Final | Passed | ||
05/22/2023 | COT - RSME - Mechanical Final | Passed | ||
05/22/2023 | COT - RSEL - Electrical Final | Passed | ||
05/22/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
05/23/2023 | RSBU - Building Final | Passed |