Permit: T22CM07460
Permit Details
Apply Date:
09/28/2022
Applicant:
Charles Romero
Description:
New Commercial Shell bldg
Permit Reviews
Permit Number - T22CM07460
Permit Status: Complete
Permit Description: New Commercial Shell bldg
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/28/2022 | 3RD PARTY REVIEW - COMMERCIAL | 10/14/2022 | ACTIVE |
09/13/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/13/2023 | REQUIRES RESUBMIT |
03/16/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/16/2024 | REQUIRES RESUBMIT |
03/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/11/2024 | APPROVED |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 04/26/2023 | REQUIRES RESUBMIT |
11/21/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/05/2024 | APPROVED |
05/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/02/2024 | APPROVED |
04/19/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/24/2024 | APPROVED |
10/23/2023 | RESTAMP - COMMERCIAL v.1 | 10/24/2023 | APPROVED |
09/14/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/29/2023 | APPROVED |
10/03/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/23/2023 | APPROVED |
05/11/2023 | RESTAMP - COMMERCIAL v.1 | 05/12/2023 | APPROVED |
05/03/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/11/2023 | APPROVED |
04/24/2024 | RESTAMP - COMMERCIAL v.1 | 04/25/2024 | APPROVED |
09/01/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/11/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM07460
Permit Status: Complete
Permit Description: New Commercial Shell bldg
Date | Description | Comments |
---|---|---|
04/26/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/26/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/26/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
04/26/2023 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. | |
04/26/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
11/21/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
03/11/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM07460
Permite Description: New Commercial Shell bldg
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/15/2023 | COT - HCPL - Yard Water Line | N/A | Partial Pass | under slab only |
10/13/2023 | COT - HCBU - Framing | N/A | Partial Pass | Exterior shear and exterior frame hold downs. |
08/09/2023 | COT - HCEL - Electrical Intermediate | N/A | Not Ready | |
02/20/2024 | COT - HCPL - Backwater Valve | N/A | Not Applicable | |
10/25/2023 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 10/24/23 partial approval for roof drains in wall and above head for mainline and hose bibs on exterior walls OK to proceed |
COT - FCON - Fire - Final | N/A | Not Ready | ||
08/15/2023 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | for footing UFER connection |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07460
Permit Description: New Commercial Shell bldg
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/15/2023 | COT - HCBU - Preslab | Passed | ||
08/15/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
08/15/2023 | COT - HCEL - Electrical Underground | Passed | for primary conduits from switch to transformer | |
12/29/2023 | COT - HCPL - Yard Water Line | Passed | ||
12/29/2023 | COT - HCBU - Framing | Passed | ||
12/29/2023 | COT - HCBU - Roof Nailing | Passed | ||
12/29/2023 | COT - HCPL - Rough Soil | Passed | ||
12/29/2023 | COT - HCPL - Sewer | Passed | ||
12/29/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
01/10/2024 | BULD - Electrical Clearance | Passed | Approved new 2000A service entrance and 400A CT cans for (5) panels, ECO Clearance to TEP is required for unit #House, unit #1, unit #2, unit #3, unit #4 | |
01/30/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
02/12/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
02/12/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
02/12/2024 | COT - HCME - Mechanical Final | Passed | ||
02/20/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
03/04/2024 | COT - BULD - SWG Clearance | Passed | ||
03/04/2024 | COT - HCEL - Electrical Final | Passed | ||
03/04/2024 | COT - HCPL - Gas Final | Passed | ||
03/06/2024 | COT - HCPL - Plumbing Final | Passed | ||
03/06/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
03/07/2024 | COT - FCON - Fire - Final | Passed | ||
04/02/2024 | COT - HCBU - Building Final | Passed | ||
04/30/2024 | COT - HCEL - Grounding/Bonding | Passed |