Permit: T22CM07134
Permit Details
Apply Date:
09/16/2022
Applicant:
Andrea Flood
Description:
SFR F40F22 T22-M0026
Permit Reviews
Permit Number - T22CM07134
Permit Status: Complete
Permit Description: SFR F40F22 T22-M0026
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/09/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/10/2023 | APPROVED |
Conditions
Permit Number - T22CM07134
Permit Status: Complete
Permit Description: SFR F40F22 T22-M0026
Date | Description | Comments |
---|---|---|
09/16/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
09/16/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
09/16/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
10/10/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
10/10/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
09/16/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. | |
10/10/2023 | Post-Tension Inspection Report is required. | |
10/10/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
10/10/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM07134
Permite Description: SFR F40F22 T22-M0026
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07134
Permit Description: SFR F40F22 T22-M0026
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/13/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/13/2022 | COT - RSPL - Sewer | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/13/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/19/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - RSBU - Preslab | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/25/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
01/25/2023 | COT - RSBU - Roof Nailing | Passed | ||
03/28/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
03/28/2023 | COT - RSEL - Construction Power | Passed | TEP ECO | |
03/28/2023 | RSME - Mechanical Progress | Passed | ||
03/29/2023 | COT - LCBU - Framing | Passed | ||
03/29/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
03/29/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
04/17/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
06/20/2023 | COT - RSPL - Plumbing Final | Passed | ||
07/20/2023 | COT - RSEL - Electrical Final | Passed | ||
07/20/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
07/20/2023 | COT - RSME - Mechanical Final | Passed | ||
07/20/2023 | RSBU - Building Final | Passed | ||
07/20/2023 | ENGR Engineering Final | Passed |