Permit: T22CM07131
Permit Details
Apply Date:
09/16/2022
Applicant:
Helen Ormsby
Description:
SFR DRHOH35G21 T21-M0042
Permit Reviews
Permit Number - T22CM07131
Permit Status: Issued
Permit Description: SFR DRHOH35G21 T21-M0042
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/02/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/02/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM07131
Permit Status: Issued
Permit Description: SFR DRHOH35G21 T21-M0042
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
09/16/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
09/16/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2018-112(P21WP00113) IS ACCEPTED ANDRELEASED BY PCRWRD |
Conditions
Permit Number - T22CM07131
Permit Status: Issued
Permit Description: SFR DRHOH35G21 T21-M0042
Date | Description | Comments |
---|---|---|
09/16/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM07131
Permite Description: SFR DRHOH35G21 T21-M0042
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
10/27/2022 | RSME - Mechanical Progress | N/A | Not Ready | |
03/16/2023 | COT - LCBU - Framing | N/A | Partial Pass | Partial per intermediates. |
03/16/2023 | COT - RSBU - Exterior Clips/Sheathing | N/A | Partial Pass | Partial pass. Need an engineer approval on a STHD hold down in back door that was not in proper place to be nailed to studs. 3/16/2023 |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM07131
Permit Description: SFR DRHOH35G21 T21-M0042
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/22/2023 | COT - RSPL - Yard Water Line | Passed | waterlines are connected to meter. Okay to backfill trenches. | |
02/22/2023 | COT - RSPL - Rough Soil | Passed | Underground plumbing is holding water. Okay to backfill trenches. | |
02/22/2023 | COT - RSPL - Sewer | Passed | ||
02/27/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
02/28/2023 | COT - RSEL - Electrical Underground | Passed | ||
03/02/2023 | COT - RSBU - Preslab | Passed | 3-2-23: Corrections completed. Per builder, j-bolts will be installed in lieu of masa straps. | |
03/02/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 3-2-23: Corrections completed. Per builder, j-bolts will be installed in lieu of masa straps. | |
03/16/2023 | COT - RSBU - Roof Nailing | Passed | ||
03/16/2023 | COT - RSEL - Construction Power | Passed | Clearance for TEP ECO. 3/16/2023 | |
04/03/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
04/03/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
04/03/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
04/10/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
04/14/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
06/07/2023 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 6/7/2023 | |
06/23/2023 | COT - RSPL - Plumbing Final | Passed | ||
06/23/2023 | COT - RSEL - Electrical Final | Passed | ||
06/23/2023 | RSBU - Building Final | Passed | ||
06/23/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
06/23/2023 | COT - RSME - Mechanical Final | Passed |