Permit Details

Status:
Complete
Type:
Commercial Building
Address:
4040 N ORACLE RD
Apply Date:
08/29/2022
Applicant:
Eduardo Araiza
Description:
TI: TARGET

Permit Reviews

Permit Number - T22CM06676
Permit Status: Complete
Permit Description: TI: TARGET
Start Date Submittal Complete Date Status  
08/29/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 09/27/2022 COMPLETED Review Details
10/10/2022 RESUBMITTAL 10/20/2022 COMPLETED Review Details
05/17/2023 RESTAMP - COMMERCIAL v.1 05/17/2023 APPROVED Review Details
09/27/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/28/2023 REQUIRES RESUBMIT Review Details
10/16/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 10/17/2023 APPROVED Review Details
05/03/2023 COMMERCIAL REVIEW - FULL v.1 05/17/2023 APPROVED Review Details

Conditions

Permit Number - T22CM06676
Permit Status: Complete
Permit Description: TI: TARGET
Date Description Comments
10/20/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
10/20/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/20/2022 SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED.
10/20/2022 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
10/20/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/29/2022 GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE
10/20/2022 SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION
10/20/2022 SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION.
02/14/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM06676
Permite Description: TI: TARGET
Total Outstanding Inspections - 12
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCEL - Service Upgrade N/A Not Ready
03/15/2023 COT - LCEL - Electrical Above Ceiling N/A Partial Pass All exterior and interior lights are installed and operational.
04/12/2023 COT - HCBU - Interior Shear Bracing N/A Partial Pass for sub structure pre curb on two RTU’S
04/13/2023 COT - LCPL - Plumbing Above Ceiling N/A Partial Pass Starbucks area OK to install hard lid
05/25/2023 COT - LCEL - Electrical Intermediate N/A Partial Pass for dairy area
06/01/2023 COT - LCBU - Framing N/A Partial Pass partial approval for training lounge ok to drywall all areas except above ceiling
06/01/2023 COT - LCEL - Electrical Progress N/A Partial Pass partial approval for training lounge ok to drywall all areas except above ceiling
06/01/2023 COT - LCPL - Plumbing Progress N/A Partial Pass GOU OH supply for hose bib complete ok to insulate also eye wash station in west closet partial approval for training lounge ok to drywall all areas except above ceiling
08/29/2023 COT - LCPL - Plumbing Intermediate N/A Partial Pass for deli/bakery
09/06/2023 COT - LCBU - Building Above Ceiling N/A Partial Pass 9/06/23 ok to install ceiling tiles
05/25/2023 COT - LCME - Mechanical Intermediate N/A Partial Pass partial approval for dairy area
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM06676
Permit Description: TI: TARGET
Total Completed Inspections - 11
Date Description Inspector Results Comments
05/26/2023 COT - HCEL - Electrical Above Ceiling Passed Electrical rough-in above hard lid ceiling in optical center is complete. Okay to proceed with installation of sheet rock for ceiling.
05/26/2023 COT - HCEL - Electrical Intermediate Passed Electrical rough-in for walls in optical center is complete. Okay to proceed with installation of sheet rock for walls.
06/07/2023 COT - LCME - Mechanical Progress Passed
06/12/2023 COT - LCME - Mechanical Above Ceiling Passed 6-12-23: Passed mechanical above ceiling in employee lounge. Okay to proceed.
07/13/2023 COT - LCPL - Plumbing Progress Passed
09/07/2023 COT - LCBU - Preslab Passed
09/07/2023 COT - LCBU - Building Progress Passed
09/15/2023 COT - LCPL - Plumbing Final Passed 9/15/23: plumbing finalized
09/18/2023 COT - LCME - Mechanical Final Passed
09/18/2023 COT - LCEL - Electrical Final Passed
09/18/2023 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
CITY OF TUCSON SI CERT T22CM06676 TARGET-2023-09-26_V1.PDF DOCUMENTS VIEW
TARGET TUCSON NORTH - FINAL REPORT - COMMENTS_2_V1.PDF DOCUMENTS VIEW
TURNER LABORATORIES CHLORINATION REPORT - TARGET T2140_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
F111_FIRE PROTECTION PLAN_V1.PDF DOCUMENTS VIEW
2140_CC10094_NARR_MECH_V1.PDF DOCUMENTS VIEW
T2140 TUCSONNORTHAZ REVISIONLETTER_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
ELECTRICAL COMCHECK.PDF DOCUMENTS VIEW
MECHANICAL COMCHECK.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
SPECIFICATIONS.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW