Permit: T22CM06675
Permit Details
Apply Date:
08/29/2022
Applicant:
Description:
TI: RETAIL
Permit Reviews
Permit Number - T22CM06675
Permit Status: Complete
Permit Description: TI: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/29/2022 | COMMERCIAL - TI | 09/23/2022 | COMPLETED |
| 09/28/2022 | RESUBMITTAL | 10/11/2022 | COMPLETED |
| 02/06/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/07/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM06675
Permit Status: Complete
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 09/15/2022 | AIR BALANCE REPORT REQUIRED |
| 09/15/2022 | WATER DISINFECTION REPORT REQUIRED |
Conditions
Permit Number - T22CM06675
Permit Status: Complete
Permit Description: TI: RETAIL
| Date | Description | Comments |
|---|---|---|
| 08/29/2022 | GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06675
Permite Description: TI: RETAIL
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/19/2023 | COT - LCPL - Yard Water Line | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06675
Permit Description: TI: RETAIL
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 11/14/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
| 11/14/2022 | COT - LCBU - Framing | Passed | ||
| 11/14/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 11/14/2022 | COT - LCME - Mechanical Intermediate | Passed | ||
| 01/19/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 01/19/2023 | COT - FCON - Fire - Final | Passed | ||
| 01/19/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 01/19/2023 | COT - LCBU - Building Progress | Passed | ||
| 01/19/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
| 01/19/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/24/2023 | COT - LCBU - Building Final | Passed | ||
| 01/24/2023 | COT - LCEL - Electrical Final | Passed | ||
| 01/24/2023 | COT - LCME - Mechanical Final | Passed |