Permit: T22CM06663
Permit Details
Apply Date:
08/29/2022
Applicant:
Description:
TI: BEAMING WELLNESS
Permit Reviews
Permit Number - T22CM06663
Permit Status: In review
Permit Description: TI: BEAMING WELLNESS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/29/2022 | COMMERCIAL - TI | 09/22/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM06663
Permit Status: In review
Permit Description: TI: BEAMING WELLNESS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/20/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T22CM06663
Permit Status: In review
Permit Description: TI: BEAMING WELLNESS
Date | Description | Comments |
---|---|---|
08/29/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: In Review
Permit Number: T22CM06663
Permite Description: TI: BEAMING WELLNESS
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
12/28/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | City approved plans are not on site |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
01/19/2023 | COT - FCON - Sprinkler - Final | N/A | Not Applicable | No work done on the fire sprinklers. |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready |
Completed Inspections
Permit Status: In Review
Permit Number: T22CM06663
Permit Description: TI: BEAMING WELLNESS
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/29/2022 | COT - LCBU - Building Above Ceiling | Passed | ||
12/29/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
01/19/2023 | COT - LCME - Mechanical Final | Passed | ||
01/19/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
01/19/2023 | COT - FCON - Fire - Final | Passed | ||
01/19/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
01/19/2023 | COT - LCBU - Framing | Passed | ||
01/19/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
01/27/2023 | COT - LCBU - Building Final | Passed | ||
01/27/2023 | COT - LCPL - Plumbing Final | Passed | ||
01/27/2023 | COT - LCEL - Electrical Final | Passed |