Permit: T22CM06354
Permit Details
Apply Date:
08/18/2022
Applicant:
thomas sayler-brown
Description:
Landlord Improvement for a Gray Shell
Permit Reviews
Permit Number - T22CM06354
Permit Status: Complete
Permit Description: Landlord Improvement for a Gray Shell
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/18/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/21/2022 | COMPLETED |
09/29/2022 | RESUBMITTAL | 10/11/2022 | COMPLETED |
10/18/2022 | RESUBMITTAL | 10/18/2022 | ACTIVE |
12/02/2022 | COMMERCIAL REVIEW - FULL v.2 | 12/08/2022 | REQUIRES RESUBMIT |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/07/2022 | REQUIRES RESUBMIT |
12/19/2022 | COMMERCIAL REVIEW - FULL v.3 | 01/03/2023 | APPROVED |
Conditions
Permit Number - T22CM06354
Permit Status: Complete
Permit Description: Landlord Improvement for a Gray Shell
Date | Description | Comments |
---|---|---|
08/18/2022 | GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06354
Permite Description: Landlord Improvement for a Gray Shell
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/29/2023 | COT - FCON - Alarm - Final | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06354
Permit Description: Landlord Improvement for a Gray Shell
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/25/2023 | COT - LCEL - Electrical Underground | Passed | Approved, okay to backfill and place concrete | |
01/25/2023 | COT - LCPL - Rough Soil | Passed | Approved, okay to shade and place concrete | |
02/15/2023 | COT - HCME - Mechanical Intermediate | Passed | Mechanical ductwork is complete. registers are installed in framing for hard lid ceilings. thermostat wiring is ran to location of thermostat. | |
02/15/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | All plumbing pipes in ceiling are properly installed and supported. okay to insulate and sheet rock ceilings. | |
02/15/2023 | COT - HCPL - Plumbing Intermediate | Passed | Plumbing rough-in is complete. Okay to insulate and sheet rock walls. | |
02/15/2023 | COT - HCPL - Plumbing Progress | Passed | Plumbers are trenching for main water supply line from meter to building. Interior waterlines are under 45# of air pressure. Gas line is under 15# of air pressure. | |
02/15/2023 | COT - HCEL - Electrical Intermediate | Passed | Electrical rough-in is complete. Boxes are properly installed conduit and mc cable are properly supported per code. Okay to cover-up with sheet rock. | |
02/15/2023 | COT - HCBU - Framing | Passed | metal framing is installed for break room and restrooms. | |
02/22/2023 | COT - HCPL - Yard Water Line | Passed | ||
03/03/2023 | COT - LCPL - Gas Pressure Test | Passed | Gas line is holding 15# of compressed air with no leaks. | |
03/03/2023 | COT - BULD - SWG Clearance | Passed | Gas line is holding 15# of compressed air with no leaks. | |
03/03/2023 | COT - LCPL - Plumbing Progress | Passed | Water back flow valve is installed. Water lines are connected to domestic water meter. | |
03/03/2023 | COT - HCEL - Electrical Above Ceiling | Passed | Electrical above ceiling matches plans. | |
03/27/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
03/27/2023 | COT - HCBU - Interior Shear Bracing | Passed | Not required no interior shear walls on project. | |
03/27/2023 | COT - HCEL - Electrical Progress | Passed | ||
03/27/2023 | COT - HCME - Mechanical Progress | Passed | ||
03/27/2023 | COT - HCBU - Building Final | Passed | Construction is complete. Okay to issue a Level 4 Certificate of Occupancy. | |
03/27/2023 | COT - HCEL - Electrical Final | Passed | Electrical panels are properly labeled. Emergency lighting is installed and operational. Electrical outlets are installed and operational. | |
03/27/2023 | COT - HCME - Mechanical Final | Passed | Mechanical equipment is installed and operational. | |
03/27/2023 | COT - HCPL - Plumbing Final | Passed | Plumbing fixtures are installed and operational. Emergency eye wash is installed and operational. | |
03/27/2023 | COT - HCBU - Building Progress | Passed | Project is complete with a few punch list items to be completed. Fire Marshal approved building on Friday 3-24-23. | |
03/29/2023 | COT - FCON - Sprinkler - Final | Passed | ||
03/29/2023 | SITE - Zoning Final | Passed |