Permit: T22CM06284
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
532 E MOHAVE RD UNIT 1
Address NEW:
532 E MOHAVE RD UNIT 1
Apply Date:
08/16/2022
Applicant:
Elan Spreiser
Description:
SFR Remodel into Duplex
Permit Reviews
Permit Number - T22CM06284
Permit Status: Complete
Permit Description: SFR Remodel into Duplex
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/16/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 09/19/2022 | COMPLETED |
| 12/21/2022 | RESIDENTIAL NEW DWELLING v.1 | 01/19/2023 | APPROVED |
| 03/23/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/28/2023 | APPROVED |
Conditions
Permit Number - T22CM06284
Permit Status: Complete
Permit Description: SFR Remodel into Duplex
| Date | Description | Comments |
|---|---|---|
| 09/15/2022 | FUP T22OT00621 MUST BE PAID IN FULL BEFORE FINAL INSPECTION | |
| 01/19/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06284
Permite Description: SFR Remodel into Duplex
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2023 | RSBU - Building Final | N/A | Re-inspection required | 1-Obtain approval of all other inspections. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06284
Permit Description: SFR Remodel into Duplex
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/02/2023 | COT - RSPL - Rough Soil | Passed | ||
| 03/10/2023 | COT - RSBU - Preslab | Passed | okay for concrete placement | |
| 03/10/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | okay for concrete placement | |
| 03/10/2023 | COT - RSPL - Yard Water Line | Passed | ||
| 03/10/2023 | COT - RSPL - Sewer | Passed | Approved from home to HCS clay connection, okay to backfill progress areas | |
| 07/17/2023 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. Units A and B. 7/17/2023 | |
| 09/27/2023 | COT - RSME - Mechanical Final | Passed | ||
| 09/27/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 09/27/2023 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 10/02/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 10/09/2023 | COT - RSEL - Electrical Final | Passed | Corrections were made . 10/9/2023 | |
| 10/09/2023 | COT - RSEL - Electrical Underground | Passed | n/a | |
| 10/09/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
| 10/09/2023 | RSBU - Building Final | Passed | Corrections were made . 10/9/2023 |