Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM06030
Permit Details
Apply Date:
08/08/2022
Applicant:
Audie Batsford
Description:
Remodel Bathrooms
Permit Reviews
Permit Number - T22CM06030
Permit Status: Complete
Permit Description: Remodel Bathrooms
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/29/2022 | COMMERCIAL - TI | 09/20/2022 | COMPLETED |
| 09/25/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/25/2023 | APPROVED |
| 11/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/21/2023 | APPROVED |
| 02/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/06/2024 | APPROVED |
| 05/10/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/14/2023 | APPROVED |
| 01/24/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/10/2023 | APPROVED |
| 11/22/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/28/2023 | APPROVED |
Conditions
Permit Number - T22CM06030
Permit Status: Complete
Permit Description: Remodel Bathrooms
| Date | Description | Comments |
|---|---|---|
| 02/09/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 06/13/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
| 02/09/2023 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 06/13/2023 | SUBMISSION OF SPECIAL INSPECTION FOR WELDING REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM06030
Permite Description: Remodel Bathrooms
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/24/2023 | COT - HCPL - Rough Soil | N/A | Re-inspection required | |
| 07/24/2023 | COT - HCPL - Plumbing Intermediate | N/A | Not Ready | |
| 11/27/2023 | COT - HCPL - Plumbing Final | N/A | Re-inspection required | Sink in ADA to high 11/27/23: seat missing at ADA shower, grab bars at ADA shower missing per plan. |
| 11/27/2023 | COT - HCBU - Building Final | N/A | Re-inspection required | Sink in ADA to high 11/27/23: seat missing at ADA shower, grab bars at ADA shower missing per plan. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM06030
Permit Description: Remodel Bathrooms
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/26/2023 | COT - HCBU - Preslab | Passed | Plumbing trench has been backfilled and compacted, pipes are properly wrapped with foam wrap at point of contact with concrete. Okay to pour back concrete slab. | |
| 07/25/2023 | COT - HCPL - Rough Soil | Passed | ||
| 08/25/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 08/25/2023 | COT - HCME - Mechanical Final | Passed | ||
| 08/25/2023 | COT - FCON - Fire - Final | Passed | ||
| 08/25/2023 | COT - HCME - Mechanical Intermediate | Passed | legacy permit | |
| 08/25/2023 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/25/2023 | COT - HCBU - Building Above Ceiling | Passed | legacy permit | |
| 08/25/2023 | COT - LCEL - Electrical Above Ceiling | Passed | legacy permit | |
| 08/25/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 08/25/2023 | COT - HCBU - Framing | Passed | ||
| 08/25/2023 | COT - HCBU - Masonry Pregrout | Passed | ||
| 08/25/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 11/14/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 11/14/2023 | ENGR Engineering Final | Passed | west parking lot needs ADA van accessible parking spot | |
| 11/27/2023 | COT - LCEL - Electrical Final | Passed | ||
| 11/28/2023 | COT - HCPL - Plumbing Final | Passed | Corrections were made. 11/28/2023 | |