Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM05912
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
635 N BENTLEY AV
Address NEW:
635 N BENTLEY AV
Apply Date:
08/03/2022
Applicant:
LuAnn Barr
Description:
R - Installation of 6.80KW PV System/MPU 200A
Permit Reviews
Permit Number - T22CM05912
Permit Status: Complete
Permit Description: R - Installation of 6.80KW PV System/MPU 200A
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/03/2022 | OTHER | 08/05/2022 | COMPLETED |
| 03/16/2023 | RESIDENTIAL SOLAR v.1 | 04/13/2023 | APPROVED |
| 07/07/2023 | RESIDENTIAL SOLAR v.2 | 07/18/2023 | APPROVED |
| 07/07/2023 | RESIDENTIAL SOLAR v.1 | 07/07/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM05912
Permit Status: Complete
Permit Description: R - Installation of 6.80KW PV System/MPU 200A
| Date | Description | Comments |
|---|---|---|
| 08/05/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 08/03/2022 | THE INSTALLATION SHALL COMPLY WITH ALL APPLICABLE REQUIREMENTS OF SECTION 605.11.1 THROUGH 605.11.4 OF THE 2012 EDITION OF THE INTERNATIONAL FIRE CODE, THE INTERNATIONAL BUILDING CODE AND NFPA 70. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05912
Permite Description: R - Installation of 6.80KW PV System/MPU 200A
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| 10/26/2022 | COT - RSEL - Service Upgrade | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05912
Permit Description: R - Installation of 6.80KW PV System/MPU 200A
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/18/2023 | RSBU - Building Final | Passed | ||
| 04/18/2023 | BULD - Electrical Clearance | Passed | Approved, DGC Clearance is required to TEP for the solar meter | |
| 04/18/2023 | COT - RSEL - Electrical Final | Passed |