Permit: T22CM05661
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1001 N 9TH AV
Address NEW:
1001 N 9TH AV
Apply Date:
07/26/2022
Applicant:
James Bohlman
Description:
Living Room, Master Suite and Storage Area Addition
Permit Reviews
Permit Number - T22CM05661
Permit Status: Issued
Permit Description: Living Room, Master Suite and Storage Area Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/26/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/16/2022 | COMPLETED |
| 10/19/2022 | RESUBMITTAL | 10/20/2022 | ACTIVE |
| 10/28/2022 | RESIDENTIAL NEW DWELLING v.1 | 12/19/2022 | APPROVED |
| 01/12/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/03/2023 | APPROVED |
Conditions
Permit Number - T22CM05661
Permit Status: Issued
Permit Description: Living Room, Master Suite and Storage Area Addition
| Date | Description | Comments |
|---|---|---|
| 12/19/2022 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 02/01/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM05661
Permit Description: Living Room, Master Suite and Storage Area Addition
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/09/2023 | COT - RSPL - Rough Soil | Passed | Ok to cover progress areas. | |
| 03/22/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | This inspection to,include pre-slab. Ok to place concrete in progress areas. | |
| 04/26/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Inspection to include roof nailing. Ok to dry in roof system. Ok to cover exterior walls. | |
| 05/04/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 05/04/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/01/2023 | COT - RSPL - Sewer | Passed | Both water line and sewer line are in the same trench due to physicality. Contractor would be liable if there are any issues. 6/1/2023 | |
| 06/01/2023 | COT - RSPL - Yard Water Line | Passed | Both water line and sewer line are in the same trench due to physicality. Contractor would be liable if there are any issues. 6/1/2023 | |
| 07/17/2023 | RSBU - Building Final | Passed |