Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
07/20/2022
Applicant:
Denise Dunning
Description:
SFR F60C22 T22-M0020

Permit Reviews

Permit Number - T22CM05516
Permit Status: Complete
Permit Description: SFR F60C22 T22-M0020
Start Date Submittal Complete Date Status  
07/20/2022 OTHER 08/08/2022 COMPLETED Review Details
11/14/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/14/2023 APPROVED Review Details
10/25/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/30/2023 APPROVED Review Details
11/03/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/09/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T22CM05516
Permit Status: Complete
Permit Description: SFR F60C22 T22-M0020
Date Description Comments
07/20/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
07/20/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
07/20/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/08/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE PERMIT.
10/30/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/30/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/30/2023 Post-Tension Inspection Report is required.
10/30/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
10/30/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM05516
Permite Description: SFR F60C22 T22-M0020
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM05516
Permit Description: SFR F60C22 T22-M0020
Total Completed Inspections - 24
Date Description Inspector Results Comments
09/21/2022 COT - RSPL - Yard Water Line Passed {Activity date: 09/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
09/21/2022 COT - RSPL - Sewer Passed {Activity date: 09/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
09/21/2022 COT - RSPL - Rough Soil Passed {Activity date: 09/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
09/30/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 09/30/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
09/30/2022 COT - RSBU - Preslab Passed {Activity date: 09/30/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
09/30/2022 COT - RSEL - Electrical Underground Passed {Activity date: 09/30/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
09/30/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 09/30/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
12/13/2022 COT - RSBU - Roof Nailing Passed
01/13/2023 COT - RSBU - Exterior Clips/Sheathing Passed
04/06/2023 RSME - Mechanical Progress Passed
04/06/2023 COT - LCBU - Framing Passed
04/06/2023 COT - RSPL - Gas Pressure Test Passed
04/10/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
04/10/2023 COT - LCPL - Plumbing Intermediate Passed
04/10/2023 COT - RSEL - Construction Power Passed
04/10/2023 BULD - Electrical Clearance Passed TEP ECO
04/26/2023 COT - HCBU - Interior Shear Bracing Passed
08/15/2023 COT - BULD - SWG Clearance Passed Swg clearance for meter only.
08/22/2023 RSBU - Building Final Passed
08/22/2023 COT - RSEL - Electrical Final Passed
08/22/2023 COT - RSME - Mechanical Final Passed
08/22/2023 ENGR Engineering Final Passed
08/22/2023 COT - FCON - Sprinkler - Final Passed
08/22/2023 COT - RSEL - Outdoor Lighting Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SITE PLAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE MANUFACTURER DELIVERY TRUSS PACKAGE_V2.PDF DOCUMENTS VIEW
CONS-152455 - SAGUARO TRAILS LOT 3329 - PT REPORT_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW