SFR PULT3519-3 T21-M0048
Outstanding Activity Conditions
Permit Number - T22CM05470
Permit Status: Issued
Permit Description: SFR PULT3519-3 T21-M0048
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
07/19/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
07/19/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
07/19/2022 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
07/19/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020-089/P21WP00061 IS ACCEPTED AND RELEASED BY PCRWRD AND NO FINAL UNTIL THE DOWNSTREAMOFFSITE PUBLIC SEWER FOR PARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM05470
Permite Description: SFR PULT3519-3 T21-M0048
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
03/17/2023 | COT - RSEL - Electrical Final | N/A | Re-inspection required | wrong size breaker for A/C UNIT door bell does not work |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM05470
Permit Description: SFR PULT3519-3 T21-M0048
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/10/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/10/2022 | COT - RSPL - Sewer | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/10/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/17/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/17/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/17/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/17/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
09/27/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/27/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 09/23/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Not ready. Canceled per contractor.} | |
09/27/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/27/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 09/23/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Not ready. Canceled per contractor.} | |
12/14/2022 | COT - RSEL - Construction Power | Passed | clearance for TEP ECO. | |
12/14/2022 | COT - RSPL - Gas Pressure Test | Passed | holding 15 psi. | |
12/15/2022 | COT - LCBU - Framing | Passed | ||
12/15/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
12/15/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
12/15/2022 | RSME - Mechanical Progress | Passed | ||
01/17/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
03/17/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
03/17/2023 | COT - RSME - Mechanical Final | Passed | ||
03/17/2023 | ENGR Engineering Final | Passed | ||
03/22/2023 | RSBU - Building Final | Passed | Approved. Corrections were made. 3/23/2023 | |
03/22/2023 | COT - RSPL - Plumbing Final | Passed | Approved. Corrections were made. 3/23/2023 |