Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
07/19/2022
Applicant:
Description:
SFR 235.2960 T21-M0055

Permit Reviews

Permit Number - T22CM05463
Permit Status: Complete
Permit Description: SFR 235.2960 T21-M0055
Start Date Submittal Complete Date Status  
07/19/2022 OTHER 08/08/2022 COMPLETED Review Details
04/28/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/02/2023 APPROVED Review Details
09/28/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/29/2023 APPROVED Review Details
09/19/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 09/20/2024 APPROVED Review Details
08/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/16/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T22CM05463
Permit Status: Complete
Permit Description: SFR 235.2960 T21-M0055
Date Description Comments
07/19/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
07/19/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
07/19/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/19/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-059/P21WP00060, G-20-089/P21WP00061 AND THE DOWNSTREAM OFFSITE PUBLIC SEWER FORPARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD
09/29/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
09/29/2023 Post-Tension Inspection Report is required.
09/29/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
05/02/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM05463
Permite Description: SFR 235.2960 T21-M0055
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
06/21/2024 COT - RSPL - Gas Pressure Test N/A Not Ready 6/21/24: not ready
06/21/2024 RSME - Mechanical Progress N/A Not Ready
06/21/2024 COT - LCPL - Plumbing Intermediate N/A Not Ready 6/21/24: not ready
06/21/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Not Ready 6/21/24: not ready
06/21/2024 COT - RSBU - Exterior Clips/Sheathing N/A Not Ready 6/21/24: not ready
06/21/2024 COT - RSEL - Construction Power N/A Not Ready 6/21/24: not ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM05463
Permit Description: SFR 235.2960 T21-M0055
Total Completed Inspections - 23
Date Description Inspector Results Comments
05/02/2024 COT - RSPL - Rough Soil Passed
05/02/2024 COT - RSPL - Yard Water Line Passed
05/02/2024 COT - RSPL - Sewer Passed
05/14/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
05/14/2024 COT - RSEL - Grounding/Bonding Passed
05/14/2024 COT - RSBU - Preslab Passed
05/14/2024 COT - RSEL - Electrical Underground Passed
05/28/2024 COT - LCBU - Framing Passed
05/28/2024 COT - RSBU - Roof Nailing Passed
06/26/2024 COT - RSPL - Gas Pressure Test Passed
06/26/2024 RSME - Mechanical Progress Passed
06/28/2024 COT - LCPL - Plumbing Intermediate Passed Corrections were made. 6/28/2024
06/28/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Corrections were made. 6/28/2024
06/28/2024 COT - RSBU - Exterior Clips/Sheathing Passed Approved per Ricky Ordóñez. 6/28/2024
07/02/2024 COT - RSEL - Construction Power Passed Clearance for TEP ECO. 7/2/2024
07/16/2024 COT - HCBU - Interior Shear Bracing Passed
08/21/2024 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 8/21/2024
09/11/2024 COT - RSPL - Plumbing Final Passed
09/11/2024 ENGR Engineering Final Passed
09/11/2024 COT - RSEL - Electrical Final Passed
09/11/2024 COT - RSEL - Outdoor Lighting Passed
09/11/2024 COT - RSME - Mechanical Final Passed
09/17/2024 RSBU - Building Final Passed Approved. Corrections were made. 9/17/2024

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SITE PLAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
2024-09-05-MERITAGE HOMES-LA ESTANCIA SOUTH PARCEL 3-LOT 61-PLAN 235.2690B TENDON ELONGATION LETTER-2024-09-06_V2.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
147585 PT LOT 61 COMPLETE-2024-08-13_V1.PDF DOCUMENTS VIEW
2024-09-05-MERITAGE HOMES-LA ESTANCIA SOUTH PARCEL 3-LOT 61-PLAN 235.2690B TENDON ELONGATION LETTER-2024-09-06_V2.PDF DOCUMENTS VIEW
CONS-LOT 61 SPECIAL INSPECTION CERTIFICATE_V1.PDF DOCUMENTS VIEW
PATTISON SIC LETTER 9.27.23_V1.PDF DOCUMENTS VIEW
LOT 61 REVISED SPECIAL INSPECTION CERTIFICATE-2023-04-25_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW