Permit: T22CM05448
Permit Details
Apply Date:
07/19/2022
Applicant:
Description:
SFR 235.2960 T21-M0055
Permit Reviews
Permit Number - T22CM05448
Permit Status: Issued
Permit Description: SFR 235.2960 T21-M0055
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/19/2022 | OTHER | 08/08/2022 | COMPLETED |
04/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/02/2023 | APPROVED |
02/07/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/07/2024 | APPROVED |
09/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/29/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM05448
Permit Status: Issued
Permit Description: SFR 235.2960 T21-M0055
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/19/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020-059/P21WP00060, G-20-089/P21WP00061 AND THE DOWNSTREAM OFFSITE PUBLIC SEWER FORPARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD |
Conditions
Permit Number - T22CM05448
Permit Status: Issued
Permit Description: SFR 235.2960 T21-M0055
Date | Description | Comments |
---|---|---|
07/19/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
07/19/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
09/29/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
02/07/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
02/07/2024 | Post-Tension Inspection Report is required. | |
09/29/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
09/29/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM05448
Permite Description: SFR 235.2960 T21-M0055
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM05448
Permit Description: SFR 235.2960 T21-M0055
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/06/2023 | COT - RSPL - Rough Soil | Passed | Underground plumbing is under a water test and connected to main sewer line. Okay to shade pipes and backfill trenches. | |
12/06/2023 | COT - RSPL - Yard Water Line | Passed | Main water line is connected to meter and under line pressure. Okay to shade pipe and backfill trench. | |
12/06/2023 | COT - RSPL - Sewer | Passed | Underground plumbing is under a water test and connected to main sewer line. Okay to shade pipes and backfill trenches. | |
12/20/2023 | COT - RSBU - Preslab | Passed | ||
12/20/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
12/20/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
12/20/2023 | COT - RSEL - Electrical Underground | Passed | ||
01/11/2024 | COT - RSBU - Roof Nailing | Passed | ||
01/16/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/07/2024 | COT - RSEL - Construction Power | Passed | ||
02/27/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
02/29/2024 | COT - LCBU - Framing | Passed | ||
02/29/2024 | RSME - Mechanical Progress | Passed | ||
02/29/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
03/01/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
03/18/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
04/26/2024 | COT - BULD - SWG Clearance | Passed | ||
05/15/2024 | COT - RSPL - Plumbing Final | Passed | ||
05/15/2024 | COT - RSEL - Electrical Final | Passed | ||
05/15/2024 | COT - RSME - Mechanical Final | Passed | ||
05/15/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
05/15/2024 | ENGR Engineering Final | Passed | ||
05/15/2024 | RSBU - Building Final | Passed |