Permit: T22CM05344
Permit Details
Apply Date:
07/14/2022
Applicant:
Denise Dunning
Description:
SFR F50B22 T22-M0032
Permit Reviews
Permit Number - T22CM05344
Permit Status: Complete
Permit Description: SFR F50B22 T22-M0032
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/01/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/02/2023 | REQUIRES RESUBMIT |
11/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/07/2023 | APPROVED |
10/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/23/2023 | APPROVED |
Conditions
Permit Number - T22CM05344
Permit Status: Complete
Permit Description: SFR F50B22 T22-M0032
Date | Description | Comments |
---|---|---|
07/14/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
07/14/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
07/14/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
10/23/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
10/23/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
07/14/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. | |
10/23/2023 | Post-Tension Inspection Report is required. | |
10/23/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
10/23/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05344
Permite Description: SFR F50B22 T22-M0032
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05344
Permit Description: SFR F50B22 T22-M0032
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/11/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/11/2022 | COT - RSPL - Sewer | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/11/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
09/01/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/23/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
09/01/2022 | COT - RSBU - Preslab | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/23/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
09/01/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/23/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
09/01/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/23/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
01/04/2023 | COT - RSBU - Roof Nailing | Passed | ||
01/04/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/06/2023 | COT - LCBU - Framing | Passed | ||
02/06/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
02/06/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
02/06/2023 | RSME - Mechanical Progress | Passed | ||
02/08/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
02/08/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
02/08/2023 | COT - RSEL - Construction Power | Passed | ||
03/14/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
06/13/2023 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
07/18/2023 | ENGR Engineering Final | Passed | ||
07/21/2023 | COT - RSPL - Plumbing Final | Passed | ||
07/21/2023 | RSBU - Building Final | Passed | ||
07/21/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
07/21/2023 | COT - RSME - Mechanical Final | Passed | ||
07/21/2023 | COT - RSEL - Electrical Final | Passed |