Permit: T22CM05322
Permit Details
Apply Date:
07/13/2022
Applicant:
Description:
New Commercial shell bldg for future restaurant
Permit Reviews
Permit Number - T22CM05322
Permit Status: Complete
Permit Description: New Commercial shell bldg for future restaurant
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/13/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/01/2022 | COMPLETED |
08/24/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/30/2023 | APPROVED |
03/01/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/17/2023 | APPROVED |
11/17/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/28/2022 | APPROVED |
08/11/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/14/2023 | APPROVED |
07/10/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/18/2023 | APPROVED |
Conditions
Permit Number - T22CM05322
Permit Status: Complete
Permit Description: New Commercial shell bldg for future restaurant
Date | Description | Comments |
---|---|---|
12/14/2022 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
12/28/2022 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
12/14/2022 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
12/14/2022 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
12/14/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
12/14/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
12/14/2022 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
12/14/2022 | WATER STERILIZATION REPORT IS REQUIRED. | |
12/14/2022 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05322
Permite Description: New Commercial shell bldg for future restaurant
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/10/2023 | COT - HCBU - Framing | N/A | Not Ready | |
03/22/2023 | COT - HCBU - Preslab | N/A | Not Applicable | 3-22-23: N/A she'll only slab will be with TI. |
04/20/2023 | COT - HCPL - Plumbing Roof Drains | N/A | Not Applicable | 4-20-23: N/A. |
05/25/2023 | COT - HCEL - Electrical Underground | N/A | Not Ready | PARTIAL - secondary conduits and communication conduits from transformer location to building, okay to backfill progress areas 5/25/23: contractor called inspection for wrong site. This site is incorrect for this inspection. |
COT - FCON - Fire - Final | N/A | Not Ready | ||
07/10/2023 | COT - HCPL - Plumbing Final | N/A | Re-inspection required | 7/10/23: waiting on correct street address change to 5353 E. Broadway in system. Waiting on Fire Dept & Site Engineering to sign off. |
07/10/2023 | COT - HCPL - Gas Final | N/A | Re-inspection required | 7/10/23: waiting on correct street address change to 5353 E. Broadway in system. Waiting on Fire Dept & Site Engineering to sign off. |
07/10/2023 | COT - HCME - Mechanical Final | N/A | Re-inspection required | 7/10/23: waiting on correct street address change to 5353 E. Broadway in system. Waiting on Fire Dept & Site Engineering to sign off. |
07/10/2023 | COT - HCEL - Electrical Final | N/A | Re-inspection required | 7/10/23: waiting on correct street address change to 5353 E. Broadway in system. Waiting on Fire Dept & Site Engineering to sign off. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05322
Permit Description: New Commercial shell bldg for future restaurant
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/09/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
03/10/2023 | COT - HCBU - Building Progress | Passed | ||
03/10/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | 3-10-23: All except Hold downs. | |
05/17/2023 | COT - HCBU - Roof Nailing | Passed | ||
03/22/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
03/24/2023 | COT - HCPL - Plumbing Progress | Passed | ||
03/24/2023 | COT - HCPL - Sewer | Passed | ||
04/25/2023 | COT - HCEL - Electrical Progress | Passed | ||
05/17/2023 | COT - HCEL - Outdoor Lighting | Passed | ||
06/06/2023 | COT - HCPL - Gas Pressure Test | Passed | 6/6/23 - main gas feed line is passed, from future meter location to shell, and ok to backfill. Interior TI lines are on a seperate permit with tenant. |
|
06/12/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
06/12/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
07/10/2023 | COT - FCON - Fire - Final | Passed | ||
07/31/2023 | COT - HCBU - Building Final | Passed |