Permit: T22CM05214
Permit Details
Apply Date:
07/11/2022
Applicant:
Russ Salmon
Description:
SFR LENNLE4005 T22-M0049
Outstanding Activity Conditions
Permit Number - T22CM05214
Permit Status: Issued
Permit Description: SFR LENNLE4005 T22-M0049
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
07/11/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
07/11/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
07/11/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
07/11/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020-90/P21WP00062 IS ACCEPTED AND RELEASED BY PCRWRD |
07/14/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
07/14/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM05214
Permite Description: SFR LENNLE4005 T22-M0049
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - RSPL - Sewer | N/A | Not Ready | |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM05214
Permit Description: SFR LENNLE4005 T22-M0049
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/19/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/19/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/29/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/29/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/29/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/29/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/06/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/06/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
10/06/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/06/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
03/20/2023 | COT - RSEL - Construction Power | Passed | Clearance for TEP ECO. 3/29/2023 | |
03/20/2023 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 3/29/2023 | |
04/03/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Rough-in of mechanical, electrical, and plumbing is complete. Okay to insulate and sheet rock walls. | |
04/03/2023 | RSME - Mechanical Progress | Passed | All ductwork is properly installed and supported. | |
04/03/2023 | COT - LCPL - Plumbing Intermediate | Passed | Plumbing bath tub and shower pans are installed and under water test. All rough plumbing is completed. | |
04/03/2023 | COT - LCBU - Framing | Passed | Rough framing is complete. Okay to insulate and apply sheet rock to interior walls. | |
04/04/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
04/18/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
04/26/2023 | COT - RSPL - Sewer | Passed | Building is connected to main sewer line. | |
07/27/2023 | COT - BULD - SWG Clearance | Passed | Swg clearance for meter only. | |
08/08/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
08/09/2023 | ENGR Engineering Final | Passed | ||
08/09/2023 | RSBU - Building Final | Passed | ||
08/09/2023 | COT - RSEL - Electrical Final | Passed | ||
08/09/2023 | COT - RSME - Mechanical Final | Passed | ||
08/09/2023 | COT - RSPL - Plumbing Final | Passed |