Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM04994
Permit Details
Apply Date:
07/01/2022
Applicant:
Cyrus Moore
Description:
Tenant improvement changing restaurant concept
Permit Reviews
Permit Number - T22CM04994
Permit Status: Complete
Permit Description: Tenant improvement changing restaurant concept
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/01/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 09/16/2022 | COMPLETED |
09/26/2022 | RESUBMITTAL | 09/30/2022 | COMPLETED |
12/22/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/04/2023 | APPROVED |
Conditions
Permit Number - T22CM04994
Permit Status: Complete
Permit Description: Tenant improvement changing restaurant concept
Date | Description | Comments |
---|---|---|
09/30/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04994
Permite Description: Tenant improvement changing restaurant concept
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Hood System - Final | N/A | Not Ready | |
06/20/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Hinges on gate. Exit signs, EM lights is back egress hallway. Occupancy signage and POA permit. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04994
Permit Description: Tenant improvement changing restaurant concept
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/12/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
10/19/2022 | COT - LCBU - Preslab | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to place concrete in progress areas} | |
01/09/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | Ok to sheet rock and fire caulk progress areas. | |
01/20/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
01/20/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
01/20/2023 | COT - LCPL - Plumbing Progress | Passed | ||
01/20/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
01/20/2023 | COT - LCEL - Electrical Progress | Passed | ||
01/20/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
01/20/2023 | COT - LCME - Mechanical Progress | Passed | ||
02/24/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
02/24/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
02/24/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
03/14/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
03/14/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
03/14/2023 | COT - HCBU - Framing | Passed | ||
04/28/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
05/31/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
05/31/2023 | COT - LCEL - Electrical Final | Passed | ||
05/30/2023 | COT - FCON - Sprinkler - Final | Passed | ||
05/31/2023 | COT - LCEL - Outdoor Lighting | Passed | Building and patio lighting. | |
05/31/2023 | COT - LCPL - Backwater Valve | Passed | ||
05/31/2023 | COT - HCBU - Roof Nailing | Passed | ||
05/31/2023 | COT - LCBU - Building Progress | Passed | ||
05/31/2023 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
06/20/2023 | COT - FCON - Alarm - Final | Passed | ||
06/20/2023 | COT - FCON - Hood System - Final | Passed | ||
06/20/2023 | COT - LCPL - Plumbing Final | Passed | Bacteria test to be submitted to Robert Sherry. | |
06/20/2023 | COT - LCBU - Building Final | Passed | Ok to make application for Certificate of Occupancy. | |
06/20/2023 | COT - LCME - Kitchen Hood | Passed | ||
06/20/2023 | COT - LCME - Mechanical Final | Passed | Air balance test results to be submitted to Robert Sherry. | |
06/20/2023 | COT - HCBU - Building Final | Passed | Ok to make application for Certificate of Occupancy. | |
06/21/2023 | COT - FCON - Fire - Final | Passed |