Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
07/01/2022
Applicant:
Cyrus Moore
Description:
Tenant improvement changing restaurant concept

Permit Reviews

Permit Number - T22CM04994
Permit Status: Complete
Permit Description: Tenant improvement changing restaurant concept
Start Date Submittal Complete Date Status  
07/01/2022 3RD PARTY REVIEW - COMMERCIAL TI 09/16/2022 COMPLETED Review Details
09/26/2022 RESUBMITTAL 09/30/2022 COMPLETED Review Details
12/22/2022 COMMERCIAL REVIEW - FULL v.1 01/04/2023 APPROVED Review Details

Conditions

Permit Number - T22CM04994
Permit Status: Complete
Permit Description: Tenant improvement changing restaurant concept
Date Description Comments
09/30/2022 Prior to permit issuance a General Contractor Letter (GCL) is required

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04994
Permite Description: Tenant improvement changing restaurant concept
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - FCON - Sprinkler - Final N/A Not Ready
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
10/26/2022 COT - FCON - Hood System - Final N/A Not Ready
06/20/2023 COT - FCON - Fire - Final N/A Partial Pass Hinges on gate. Exit signs, EM lights is back egress hallway. Occupancy signage and POA permit.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04994
Permit Description: Tenant improvement changing restaurant concept
Total Completed Inspections - 33
Date Description Inspector Results Comments
10/12/2022 COT - LCPL - Rough Soil Passed {Activity date: 10/12/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
10/19/2022 COT - LCBU - Preslab Passed {Activity date: 10/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to place concrete in progress areas}
01/09/2023 COT - HCBU - Firewall/Fire Barrier/Firestop Passed Ok to sheet rock and fire caulk progress areas.
01/20/2023 COT - LCPL - Plumbing Intermediate Passed
01/20/2023 COT - LCEL - Electrical Intermediate Passed
01/20/2023 COT - LCPL - Plumbing Progress Passed
01/20/2023 COT - LCPL - Plumbing Roof Drains Passed
01/20/2023 COT - LCEL - Electrical Progress Passed
01/20/2023 COT - HCBU - Interior Shear Bracing Passed
01/20/2023 COT - LCME - Mechanical Progress Passed
02/24/2023 COT - LCPL - Gas Pressure Test Passed
02/24/2023 COT - LCME - Mechanical Intermediate Passed
02/24/2023 COT - LCME - Mechanical Above Ceiling Passed
03/14/2023 COT - LCBU - Building Above Ceiling Passed
03/14/2023 COT - HCBU - Building Above Ceiling Passed
03/14/2023 COT - HCBU - Framing Passed
04/28/2023 COT - LCPL - Plumbing Above Ceiling Passed
05/31/2023 COT - LCEL - Electrical Above Ceiling Passed
05/31/2023 COT - LCEL - Electrical Final Passed
05/30/2023 COT - FCON - Sprinkler - Final Passed
05/31/2023 COT - LCEL - Outdoor Lighting Passed Building and patio lighting.
05/31/2023 COT - LCPL - Backwater Valve Passed
05/31/2023 COT - HCBU - Roof Nailing Passed
05/31/2023 COT - LCBU - Building Progress Passed
05/31/2023 COT - HCBU - Stem Wall/Retaining Wall Passed
06/20/2023 COT - FCON - Alarm - Final Passed
06/20/2023 COT - FCON - Hood System - Final Passed
06/20/2023 COT - LCPL - Plumbing Final Passed Bacteria test to be submitted to Robert Sherry.
06/20/2023 COT - LCBU - Building Final Passed Ok to make application for Certificate of Occupancy.
06/20/2023 COT - LCME - Kitchen Hood Passed
06/20/2023 COT - LCME - Mechanical Final Passed Air balance test results to be submitted to Robert Sherry.
06/20/2023 COT - HCBU - Building Final Passed Ok to make application for Certificate of Occupancy.
06/21/2023 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
EQUIPMENT SPECIFICATIONS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
GCL 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PSA WILLDAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
BACTERIA FLUSH-2023-06-21_V1.PDF DOCUMENTS VIEW
AIR BALANCE_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
EQUIPMENT SPECIFICATIONS.PDF DOCUMENTS VIEW
GCL.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
PSA WILLDAN.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-REV1_1 PLAN SET_V1.PDF DOCUMENTS VIEW
REV1_1 REVISON NARRATIVE_V1.PDF DOCUMENTS VIEW