Permit: T22CM04974
Permit Details
Apply Date:
07/01/2022
Applicant:
Preston Espinosa
Description:
The proposed project is for a new drive-thru car wash facility and exterior vacuum.
Permit Reviews
Permit Number - T22CM04974
Permit Status: Complete
Permit Description: The proposed project is for a new drive-thru car wash facility and exterior vacuum.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/01/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/18/2022 | COMPLETED |
09/13/2022 | RESUBMITTAL | 09/27/2022 | COMPLETED |
02/04/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/03/2023 | REQUIRES RESUBMIT |
11/08/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/29/2022 | REQUIRES RESUBMIT |
04/19/2023 | COMMERCIAL REVIEW - FULL v.3 | 04/19/2023 | REQUIRES RESUBMIT |
06/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/22/2023 | REQUIRES RESUBMIT |
04/21/2023 | RESTAMP - COMMERCIAL v.1 | 04/21/2023 | APPROVED |
11/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/21/2023 | APPROVED |
11/22/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/28/2023 | APPROVED |
04/21/2023 | COMMERCIAL REVIEW - FULL v.4 | 04/21/2023 | APPROVED |
07/05/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/20/2023 | APPROVED |
12/05/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/05/2023 | APPROVED |
Conditions
Permit Number - T22CM04974
Permit Status: Complete
Permit Description: The proposed project is for a new drive-thru car wash facility and exterior vacuum.
Date | Description | Comments |
---|---|---|
06/09/2023 | Please submit plans with correct address prior to issuance. Please direct questions to Pima County Addressing at Addressing@pima.gov or 520-724-9512 | |
04/21/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
09/21/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
09/21/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
09/21/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
09/21/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
09/21/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
09/21/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
09/21/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
09/21/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
09/21/2022 | SPECIAL INSPECTION IS REQUIRED - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
04/21/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
04/21/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
11/28/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04974
Permite Description: The proposed project is for a new drive-thru car wash facility and exterior vacuum.
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/21/2022 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | {Activity date: 09/21/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - WATER CHLORINATIN REPORT REQUIRED PRIOR TO FINAL INSPECTION} |
06/20/2023 | COT - HCBU - Preslab | N/A | Partial Pass | 6/20/23: pre-slab for wash bay approved. |
07/21/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | canopy bases west side ok for concrete |
08/10/2023 | COT - HCBU - Roof Nailing | N/A | Partial Pass | 8/10/23: Roof nailing from office to restrooms passed |
07/13/2023 | COT - HCEL - Electrical Progress | N/A | Partial Pass | |
11/06/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | Inspection was called in to verify the electrical clearance due to the address change. Applicants need to re submit an address change to TEP for ECO clearance. 11/6/2023 |
11/14/2023 | ENGR Engineering Final | N/A | Partial Pass | Will review River rock locations and disturbed storm water drain areas for possible hydro seeding requirements. Will review NE corner drain block height . Handicap sign located at North end of vacuum station area will need to be raised to 7’ bottom of sign (height is currently at 5’-6”) at bottom of sign. Various site signs at entry and exit points are currently being installed and to be completed the 16th of this week. Inspections will be recalled on Thursday November 16 Okay for TCO level 4 |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04974
Permit Description: The proposed project is for a new drive-thru car wash facility and exterior vacuum.
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/30/2023 | COT - HCPL - Yard Water Line | Passed | ||
07/25/2023 | COT - HCBU - Masonry Pregrout | Passed | Third-party inspection | |
08/18/2023 | COT - HCBU - Framing | Passed | Restroom and office area metal stud framing is complete | |
08/18/2023 | COT - HCEL - Electrical Progress | Passed | 8/18/23: Electrical rough-in is complete in office area and bathroom. Okay to cover up with drywall. | |
08/18/2023 | COT - HCPL - Plumbing Progress | Passed | 8/18/23: Restroom plumbing is roughed in and under water test. Okay to cover up walls. | |
10/16/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
10/31/2023 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. | |
11/14/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
11/14/2023 | COT - HCEL - Electrical Underground | Passed | ||
11/15/2023 | COT - HCBU - Building Progress | Passed | ||
11/15/2023 | COT - HCBU - Building Final | Passed | ||
11/15/2023 | COT - HCEL - Electrical Final | Passed | ||
11/15/2023 | COT - HCPL - Plumbing Final | Passed | ||
11/14/2023 | COT - FCON - Fire - Final | Passed | ||
11/14/2023 | COT - HCME - Mechanical Final | Passed | ||
11/17/2023 | COT - HCPL - Sewer | Passed | ||
11/16/2023 | COT - HCEL - Outdoor Lighting | Passed | ||
12/01/2023 | ENGR Engineering Final | Passed |