Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Withdrwn
Type:
SINGLE FAMILY NEW
Apply Date:
06/23/2022
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
SFR BRIO1432 T20-M0058
Architects:
  • A23 STUDIOS

Permit Reviews

Permit Number - T22CM04777
Permit Status: Withdrwn
Permit Description: SFR BRIO1432 T20-M0058
Start Date Submittal Complete Date Status  
06/23/2022 OTHER 08/02/2022 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T22CM04777
Permit Status: Withdrwn
Permit Description: SFR BRIO1432 T20-M0058
Total Outstanding Activity Conditions - 9
Date Name
06/23/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
06/23/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
06/23/2022 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
06/23/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/23/2022 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
06/23/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/23/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
07/13/2022 WATER METER SIZE
08/02/2022 Prior to permit issuance a General Contractor Letter (GCL) is required

Outstanding Inspections

Permit Status: Withdrwn
Permit Number: T22CM04777
Permite Description: SFR BRIO1432 T20-M0058
Total Outstanding Inspections - 24
Last Inspection Date Description Inspector Results Comments
EXCAVATION/LAYOUT REBAR & ZON N/A Not Inspected
BUILDING PRE-SLAB N/A Not Inspected
EXT METAL CLIPS/EXT SHEATHING N/A Not Inspected
ROOF NAILING N/A Not Inspected
FRAMING N/A Not Inspected
STUCCO MESH N/A Not Inspected
U VALUE FOR WINDOW N/A Not Inspected
SHEET ROCK NAILING N/A Not Inspected
BUILDING - FINAL N/A Not Inspected
ELECTRIC - UFER N/A Not Inspected
ELECTRIC - UNDERGROUND N/A Not Inspected
ELECTRIC - INTERMEDIATE N/A Not Inspected
ELECTRIC - CABLE DROP N/A Not Inspected
ELECTRIC - FINAL N/A Not Inspected
PLUMBING - ROUGH, SOIL N/A Not Inspected
PLUMBING - PRE SLAB N/A Not Inspected
PLUMBING - INTERMEDIATE N/A Not Inspected
PLUMBING - YARD WTR LINE/TEST N/A Not Inspected
PLUMBING - SEWER HCS CONNECT N/A Not Inspected
SITE - SEWER N/A Not Inspected
PLUMBING - FINAL N/A Not Inspected
MECHANICAL - INTERMEDIATE N/A Not Inspected
MECHANICAL - FINAL N/A Not Inspected
ENGINEERING - FINAL N/A Not Inspected